Home » Green Ammonia Production and Plants: What the Route Choice Decides
Green Ammonia Production and Plants: What the Route Choice Decides
10 min read · Dec 2, 2025 · By Alex
I am asked how ammonia can be made without fossil feedstock, and the direct answer is short: I split water in an electrolyser, the device that uses electricity to break water apart, to obtain renewable hydrogen, I take nitrogen from the air, and I combine the two in a synthesis loop, the industrial process that combines hydrogen and nitrogen under pressure. The plant that results is decided by three choices I make before feasibility: where the power comes from, whether the site builds new or retrofits an existing unit, and what scale the offtake, the volume a buyer commits to purchase, can actually absorb. Those three choices are the spine of the green ammonia guide, and this article is my working note on green ammonia production and plants.
Below I walk through the route and the process behind it, the hydrogen that carries the carbon intensity, the plant envelope I fix first, what the market has actually sanctioned, retrofit or new build, my reading of Southeast Asia, and the four checks I run before the study closes. Every figure is dated where it appears.
In short
- Route: I settle the production route before the study, because the power behind the electrolyser decides the carbon intensity and the cost of every tonne.
- Plant envelope: I fix site, interconnection and throughput first, and I never read an announced capacity as capacity in operation.
- Hydrogen: The electrolyser stack is a minority of installed investment, so my budget is a plant budget rather than an equipment price.
- Market: Firm offtake is the scarcest input, and most announced projects have not yet committed investment.
- Sequence: I run cost of capital, budget composition, offtake evidence and site evidence in that order before the study closes.
In this article
What a green ammonia plant actually does
Green ammonia is ammonia made with renewable hydrogen instead of hydrogen from natural gas or coal. I split water in an electrolyser to obtain that hydrogen, and I take nitrogen from the air. The synthesis loop is the part of the plant that combines the two under pressure, so the product leaving the gate is chemically identical to any other ammonia. A retrofit converts an existing conventional unit rather than building a new one, and a load factor tells me how much of the year the plant runs at its rated output.
The baseline I am replacing is fossil to its core. In 2024, 99 percent of ammonia production depended on fossil inputs, split 72 percent natural gas, 26 percent coal and 1 percent oil, and the production and use of ammonia accounted for 2 percent of the world’s carbon dioxide emissions in 2024. That is why I settle the route before I let anyone scope the civil works.
What this means for you: I write the definition of the tonne I intend to make on the first page of the study, because power, water, offtake and permits all follow from that single sentence.
The route decision comes before the study
The route decides the equipment list, the power contract and the cost curve, so I settle it before anyone books a feasibility study. The January 2024 white paper from BloombergNEF and Climate Technology Coalition gives me the frame: global ammonia capacity stands at 243 million tonnes a year with China close to a third of it, grown about 1.5 percent a year since 2011 and projected at about 1 percent a year to 2032. Plants last 20 to 50 years and run at about 80 percent utilisation, so any unit I build has to live with those economics for decades. Production cost ranges from 100 to 1,000 USD a tonne by region, with an average of 305 USD a tonne since 2013.
On the other side of the ledger, green hydrogen cost is expected to fall 66 percent by 2030 to 1 to 4.1 USD per kilogram, green ammonia reaches parity with grey ammonia in some markets in 2024-2025, and it is modelled to become cheaper than grey in more than half of the 29 modelled markets from 2034. I set my route against those numbers, then I read the production process in detail.
What this means for you: I choose the route on power availability and offtake geography first, and only then do I let an engineering scope be written around it.
The plant envelope I fix first
Before any modelling I fix three physical things: the site, the interconnection and the throughput the offtake can absorb. The Hydrogen Council with McKinsey & Company roadmap of November 2025 shows why the envelope has to stay disciplined: more than 300 Mtpa of low-carbon ammonia projects had been announced by May 2025, already above the 200 Mtpa conventional market, yet only 85 projects totalling 35 Mtpa were at FEED, the front end engineering design stage, and only 48 projects totalling 15 Mtpa had reached a final investment decision, which is the point at which financing is committed and the project stops being an announcement.
Inside that announced mass, 1.3 Mtpa was already online as retrofits. New low-carbon plants reach capture rates above 95 percent and existing technologies can abate more than 80 percent of the footprint, while 35 GW of electrolysers are expected worldwide by 2030. On the demand side, in one scenario Indian imports close around 600 USD a tonne as the low end. I write the same envelope out as a plant configuration checklist.
What this means for you: I size my plant on the offtake I can evidence and on interconnection I can secure, never on the announced national pipeline.
The hydrogen behind the tonne
The carbon intensity of my ammonia follows the power behind the electrolyser, so I read the green hydrogen page next. The money does not sit where people expect: in 2025 the electrolyser stack is only 15 to 20 percent of installed investment, with most of the budget going to process balance, works and grid connection. Scale has moved quickly. The largest electrolyser was 30 MW in 2021, a 500 MW project was commissioned in China in 2025, and one project in Saudi Arabia targets 2 GW in operation by 2027, which is a 75 times increase in six years.
Manufacturing and price follow the same concentration. In 2025 China holds close to 60 percent of global electrolyser manufacturing capacity, and renewable hydrogen there is 40 to 45 percent cheaper than in Europe or the United States. I treat the power contract, not the equipment brochure, as the driver of both the tonne’s carbon intensity and its price.
What this means for you: I ask for the power contract and the connection offer before I ask for an electrolyser quotation, because the quotation is the smaller half of the installed cost.
What the market has actually sanctioned
The IEA Global Hydrogen Review 2026 reports that global hydrogen demand passed 100 Mt in 2025, that low-carbon production grew 20 percent in 2025 to almost 1 Mt, and that this share is expected to pass 1 percent of global production for the first time in 2026. The announced pipeline has fallen back to 27 Mt to 2030, with 300 ktpa of additional final investment decisions since the previous assessment, projects with high operation potential in 2030 down from 10 Mt to a little more than 6 Mt, and 22 Mt at risk of never entering service by 2030 without an investment decision before early 2027. About 80 percent of high-availability production targets chemicals, refining and low-carbon fuels.
The barriers named are high costs, uncertain demand, slow or complex regulation and insufficient infrastructure (2026). I read that list as a filter I apply to my own project before I quote a single capacity number to a buyer.
What this means for you: I keep three columns in my model, announced, at a final investment decision, and actually produced, and I never move a tonne between them to make a slide work.
Retrofit or new build
A retrofit turns a conventional unit into a low-carbon one using the existing site and its interconnection, while a new build buys a new site, a new grid connection and a new permitting cycle from scratch. An announced project stays an announcement until the investment decision is taken and the offtake is signed. The announced low-carbon pipeline included 1.3 Mtpa already online as retrofits in May 2025, the smallest share of the announced total and the closest to operating reality.
I set both options side by side as the retrofit route against a greenfield unit on the same power assumption.
- What the retrofit keeps: the site, the interconnection, the permits already granted and the operators who know the unit.
- What the new build buys: a process layout sized for the electrolyser and a scale I choose rather than inherit.
- What neither of them removes: the cost gap against the fossil baseline, which only a signed long-term offtake or a lower cost of capital closes.
What this means for you: I price both options with the same power assumption and the same offtake volume, and I decide on permitting time and interconnection rather than on the label.
What I would assume in Southeast Asia
The December 2025 Southeast Asia briefing gives me the regional baseline: hydrogen demand reached 4 Mt in 2024, with ammonia at 49 percent of that demand against refining at 31 percent and methanol at 20 percent. Indonesia takes 35 percent, Malaysia 22 percent, Viet Nam 15 percent and Singapore 12 percent. Only Indonesia and Malaysia export, with Malaysia at 73 percent of regional exports and the region at 17 percent of world ammonia exports in 2023.
Announced regional projects equal 12 percent of current demand while only 6 percent of announced capacity has reached a final investment decision. Nearly 11 Mtpa of potential sits below 6 USD/kg by 2030, mostly in Indonesia. No certification scheme is yet in place, with work under way in three countries, and 6.6 billion USD of development finance institution loans flowed from 2021 to 2025. The barriers named for the region are high cost of capital, weak renewable penetration and low incentives to switch fuel (2025). All of it becomes the context for the scale-up checklist I run on any site there.
What this means for you: I assume no certification path and no cheap capital until I hold written evidence for both, and I assume the local offtake before I assume the export route.
The four checks I run before the feasibility study closes
The first check comes from the 2025 review’s five key questions: cost of capital can reach 15 percent in emerging economies, three times the level in advanced economies, and renewable hydrogen is 40 to 45 percent cheaper in China than in Europe or the United States (2025). The second is the composition of my budget, since the electrolyser stack is 15 to 20 percent of installed investment in 2025 and my number must cover works, balance of plant and connection rather than equipment alone. The third is that announced capacity is not supply: less than 2 Mtpa of firm offtake agreements exist cumulatively, about 5 percent of potential 2030 output, and only 9 percent of announced projects worldwide have secured committed investment against 0.5 percent in emerging economies (2025). The fourth is the site, which must show its power contract and its water supply before the scale is fixed (2025).
- The route I pick: renewable hydrogen behind a contracted power supply, because the carbon intensity of the tonne is decided there and nowhere else.
- The scale I refuse to exceed: the volume my signed offtake can absorb, not the volume any announced capacity suggests.
- The order of the checks: cost of capital first, budget composition second, offtake evidence third, site evidence last.
What this means for you: I close no study until all four checks are written down with a date and a source, and I refuse to let an announced number set my scale.
Sources
- BloombergNEF and Climate Technology Coalition, Scaling Up Hydrogen: The Case for Low-Carbon Ammonia https://assets.bbhub.io/professional/sites/24/CTC-whitepaper_Ammonia_Final.pdf, January 2024.
- Hydrogen Council with McKinsey & Company, Fertilizing the future: A roadmap to scale low-emission ammonia fertilizers https://hydrogencouncil.com/wp-content/uploads/2025/11/Fertilizing-the-future-FINAL.pdf, November 2025.
- IEA, Global Hydrogen Review 2026, Executive summary https://www.iea.org/reports/global-hydrogen-review-2026/executive-summary, 2026.
- IEA, Global Hydrogen Review 2025, Southeast Asia, 9 December 2025 https://iea.blob.core.windows.net/assets/745a259b-9cb7-4e1d-9ba1-a8b63d1eaae8/GHR2025_SEA_Webinar.pdf, 2025.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
Frequently asked questions
How is green ammonia different from conventional ammonia?
The hydrogen. Conventional ammonia uses fossil feedstocks, with 99 percent of production dependent on fossil inputs split 72 percent natural gas, 26 percent coal and 1 percent oil in 2024, while green ammonia uses renewable hydrogen obtained by splitting water. The production and use of ammonia accounted for 2 percent of global carbon dioxide emissions in 2024.
What decides the size of a green ammonia plant?
Three things: the power contract behind the electrolyser, the offtake volume the market can absorb, and the site. Global ammonia capacity stands at 243 million tonnes a year at about 80 percent utilisation (2024), while only 48 projects totalling 15 Mtpa had reached a final investment decision (May 2025).
Should I retrofit an existing plant or build a new one?
A retrofit keeps the site, the interconnection and the permits and converts the unit, and 1.3 Mtpa of retrofits were already online in May 2025. A new build buys a new site, a new grid connection and a new permitting cycle, and gives me control of the process design from the start.
What is the biggest cost risk in a green ammonia plant?
The cost of capital: it can reach 15 percent in emerging economies, three times the level of advanced economies in 2025, on top of an electrolyser stack that is only 15 to 20 percent of installed investment in 2025, so the budget must cover works, balance of plant and connection rather than equipment alone.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want a second set of eyes on the route, the plant envelope and the four checks before your feasibility study closes, I run technology maturity and scale-up support as a working session on one live project, with a written output you can carry into the study.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.