Hydrogen Policy in Asia: What National Strategies Change for Your Project

10 min read  ·  Dec 2, 2025  ·  By Alex

hydrogen policy asia

Most published roadmaps in the hydrogen, power-to-liquid and e-fuels space promise volume and leave the buyer to be found later. Hydrogen policy in Asia matters only where it creates a paying buyer: on the record of the five Southeast Asian countries that already hold a national strategy. The support that actually appears is renewable deployment, cheaper capital, pilot projects, big anchor applications and certification schemes, not a purchase guarantee. I therefore treat hydrogen policy asia as a ranking problem rather than a scoreboard of ambitions, and the ranking has a fixed order.

The order is not decorative. I apply five filters to any national hydrogen policy and I never swap them. That is because a document that fails the first filter rarely survives the fifth. Each filter comes with the record that supports it.

In short

  • Demand: The policy must point to a buyer. Regional demand was 4 Mt in 2024, concentrated in ammonia, refining and methanol.
  • Balance sheet: Five planning thrusts build capability, but they do not put an obligation on any ministry.
  • Money: I count strategies and action plans as workload and ask which line is actually funded.
  • Contracts: Certification, change of law and support formulas decide whether the price I model holds.
  • Capital: Committed investment and binding purchase agreements are the only signals I trust.
Facebook
Twitter
LinkedIn

In this article

What a national hydrogen policy is supposed to do

A national strategy, as I use the term, is a published government document that names targets, assigns responsibility. In addition, lists the instruments it will use. It is neither a project list nor a budget line. Scale is checkable: in 2022, 40 countries had announced hydrogen strategies, and if all announced pipeline projects materialised. Low-carbon hydrogen production could reach up to 24 Mtpa by 2030 against less than 1 Mtpa in 2021. That scenario is conditional on announcements, not a target.

The other four terms finish the vocabulary. An anchor application is one large buyer sector, such as refining, ammonia, ports or power, that can absorb enough volume to justify a plant. A certification scheme is the set of rules proving how and where the hydrogen was made. In addition, a guarantee of origin is the document carrying that proof to the buyer. A firm purchase agreement binds volume and price, not a letter of interest.

What this means for you: I start every document with these five terms in hand. A strategy that names no anchor application and no certification path is a statement of intent, and I compare countries accordingly.

Filter one: does the policy create demand

Filter one asks whether the policy points at a buyer. The IEA briefing of 9 December 2025 gives the picture for the five Southeast Asian countries that hold a national strategy: 4 Mt of hydrogen demand in 2024. Split by use between ammonia at 49 percent, refining at 31 percent and methanol at 20 percent, and by country between Indonesia at 35 percent, Malaysia at 22 percent, Viet Nam at 15 percent and Singapore at 12 percent.

Announced regional projects equal 12 percent of that demand, and only 6 percent of announced capacity has reached a first FID, meaning the final investment decision that commits the capital. The recommendations to governments run through renewable deployment, cheaper capital, pilot projects, big anchor applications and certification schemes. Nothing there is a purchase guarantee, so I look for the instrument that turns advice into obligation: a fuel mandate with a volume behind it.

What this means for you: I do not credit a country with demand it has merely described. Until a mandate converts the 4 Mt of 2024 into a scheduled volume, it is context, not offtake.

Filter two: does it reach the buyer's balance sheet

Filter two asks whether the document reaches the buyer’s balance sheet. Singapore’s National Hydrogen Strategy of October 2022 organises its effort around five thrusts: pathfinder projects, research and development, international collaboration, long-term land and infrastructure planning, and workforce training. It assesses hydrogen at up to 50 percent of projected electricity demand by 2050, states that the mix is not fixed, and paces deployment against global and technological development.

Note what is absent: no purchase obligation, no price, no buyer named. None of the five thrusts names a price either. The thrusts build capability and land. That is real work, and they underpin the funding lines a developer can draw on. What the strategy does not do is commit anyone to take the output.

Also, What this means for you: I read the five thrusts as a capacity plan, not as credit. If a document cannot show me who signs for the tonnes and on whose balance sheet the obligation sits. I file it under preparation and keep my schedule loose.

Filter three: is there money behind the words

Filter three asks whether money sits behind the words. Malaysia’s Hydrogen Economy and Technology Roadmap of 5 October 2023 is a supporting document to the National Energy Policy running from 2022 to 2040. In addition, it sets out 5 strategic thrusts, 8 strategies and 29 action plans. That structure tells me who does what; it does not tell me what is funded.

The projections are dated and specific: revenue of up to RM12.1 billion in 2030. RM49 billion to RM61 billion added to GDP, between 8,000 and almost 45,000 jobs by 2030, more than RM400 billion of revenue and more than 200,000 jobs by 2050. The same document records that Malaysia, Indonesia, Brunei and the Philippines carried no policy, roadmap, strategy or national target at the time of writing. I find money behind renewable hydrogen projects where industrial policy does.

What this means for you: I count strategies and action plans as workload, not as cash. The figures above are projections for 2030 and 2050, so I convert them into one question: which line in the roadmap pays for my plant, and when?

Filter four: does it survive contract drafting

Filter four asks whether the policy survives contract drafting. In 2025, quality specification, emissions intensity and certification scheme are what decide commercial value. In addition, access to support regimes, so I ask for them as schedules to the contract rather than as policy intentions. I also ask that change of law clauses come first, keeping the agreement viable as subsidy regimes. In addition, carbon pricing rules evolve, while wide reopenings stay out because they undermine bankability.

Public support in 2025 is built into the price through formulas or adjustments that share the subsidy value between the parties. That means the incentive can shrink without anyone breaching. The policy risk I refuse to carry is a regime change that cuts my price while my volume obligation stays in place.

What this means for you: I read a policy. In addition, a contract in the same sitting, because support that cannot be drafted is support I cannot model. If the regime can be withdrawn while my obligation stays, I decline the structure.

Filter five: what the capital market believes

Filter five asks what the capital market believes. The IEA page of five key questions from 2025 records 9 percent of announced projects worldwide having secured committed investment against 0.5 percent in emerging economies, and firm purchase agreements cumulating to less than 2 Mtpa, only 5 percent of the production potential announced for 2030. Committed investment is money pledged, not money spent, and an agreement announced is not yet a contract.

The same page puts the cost of capital, meaning the return lenders. In addition, equity require to fund a project, at 15 percent in emerging economies in 2025. Three times the level in advanced economies. That single number rewrites every levelised cost I run. Also, that is why I pair it with my green hydrogen cost review for Southeast Asia before I compare countries.

What this means for you: I treat the 0.5 percent figure as the honest baseline for my country. In addition, I ask what would move it. A policy that lowers the required return does more for my project than one that announces volumes.

What this means for a Southeast Asian developer

The Oxford Institute for Energy Studies study of August 2025 records that hydrogen sale and purchase agreements typically run 10 to 15 years, about half the length of the first international gas and LNG contracts, with volume provisions at 60 to 80 percent take-or-pay in low-carbon hydrogen, where the buyer pays an agreed share of annual volume whether or not it is lifted, against above 90 percent in gas and LNG.

More than 5 million tonnes per year of projects reached FID in the low-carbon hydrogen trade that is about to expand. In addition, the central pricing difficulty is the absence of a transparent market price for low-carbon hydrogen. Against that gap I set the patient capital available from development lenders. That can carry tenor and risk that commercial lenders will not.

What this means for you: I size my contract against the 10 to 15 year record rather than against an ambition, and I look for a transparent price reference before I sign anything. Tenor without a price is just duration.

How I read a policy in one sitting

Two 2025 numbers frame the region. Southeast Asia holds regional potential of close to 11 Mtpa below 6 USD/kg by 2030. However, no certification scheme is in place. With work under way in three countries, and 38 billion USD of public funding has advanced since the previous assessment.

I read a policy in one sitting and in three passes: first the demand section, then the money section, then the contracting and certification sections. I write five words in the margin, demand, buyer, money, contract, capital, and tick each only when the document names a mechanism rather than an intention. What is left unread usually decides the call, so the certification section never waits for a second sitting.

Also, What this means for you: I finish one sitting with a country either on the list or off it. In addition, I can show you the five marginal words that produced the call. Certification and public funding tell me the direction; only the first three passes tell me whether to go.

Sources

Frequently asked questions

Five Southeast Asian countries held a national strategy in the record of December 2025, and 40 countries worldwide had announced strategies in 2022. The demand sits with them: 4 Mt in 2024, split between Indonesia at 35 percent, Malaysia at 22 percent, Viet Nam at 15 percent and Singapore at 12 percent. A strategy holder is not automatically a buyer.

It changes the demand side and the cost of capital, and it can schedule volumes. A strategy of October 2022 assesses hydrogen at up to 50 percent of projected electricity demand by 2050, and a roadmap of 5 October 2023 sets an export schedule of 0.5 to 1 MTPA by 2030. Neither figure is a contract, but both change who I call first.

No. In 2025 support is built into the price through formulas that share subsidy value between the parties, while the contract still has to carry the volume and the change of law risk. A subsidy that can be recalculated is a price assumption, not a guarantee of purchase.

I read it for five things in order: created demand, balance sheet behind the buyer, money behind the words, survival through contract drafting, and what the capital market believes. I give the document one sitting, and a policy that fails the first filter rarely survives the fifth.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are choosing between countries at pre-FID stage, the fastest way to see what a policy pays for is grant. In addition, incentive mapping against your project’s actual cost stack. I run that comparison with your team, using the five filters above. In addition, I hand back a short list with each funding line named.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial. In addition, financial partners needed to reach FID.