Home » Methanol vs LNG as Marine Fuel: Four Numbers That Decide It
Methanol vs LNG as Marine Fuel: Four Numbers That Decide It
10 min read · Nov 2, 2026 · By Alex
Methanol or LNG (liquefied natural gas): four dated numbers decide it. The orderbook, meaning ships on order, shows 188 LNG orders in 2025 for 31 percent of total gross tonnage. That tonnage is the summed enclosed volume, and methanol took 61 orders, down from 149 in 2024. Tank volume: methanol needs about 2.4 times the space of a marine gas oil (MGO) ship. It sits at 20 degrees Celsius instead of minus 162 degrees. Price: 700 USD a tonne of fossil methanol in Asia-Pacific in November 2026. Regulation: 39 EUR a tonne of non-compliance cost on fossil fuel in 2025. That penalty for missing an emissions target reaches 353 EUR in 2035 and 1,997 EUR in 2050. That is my sustainable maritime fuels framing for methanol vs lng marine fuel at concept stage.
How I compare methanol vs LNG marine fuel on four dated numbers
In fact, reputation decides nothing at this stage. A fuel’s image does not tell me how much volume the vessel gives up, what a posted price sheet says, or what the rule adds per tonne across the asset life. Therefore, I work only from dated, published records.
In short
- Orderbook: 188 LNG orders in 2025 for 31 percent of gross tonnage; 61 methanol orders, down from 149 in 2024.
- Tank volume: about 2.4 times the marine gas oil tank space, recorded in May 2023, held at 20 degrees Celsius instead of minus 162 degrees.
- Price: about 700 USD a tonne of fossil methanol in Asia-Pacific in November 2026.
- Compliance: 39 EUR a tonne on fossil fuel in 2025, 353 EUR in 2035, 1,997 EUR in 2050.
- Delivery: 59 methanol-fuelled ships delivered in 2025 and 38 in the first half of 2026, against 22 LNG bunker vessels added to the orderbook in 2025.
In this article
What the comparison has to decide
I answer the concept-stage question directly. On the orderbook LNG leads, on tank volume methanol costs space, and on price fossil methanol reads about 700 USD a tonne in Asia-Pacific in November 2026. On regulation, fossil fuel carries 39 EUR a tonne in 2025, rising to 1,997 EUR a tonne in 2050. Orderbook means ships on order; gross tonnage means the summed enclosed volume they occupy. Therefore, I compare shares rather than hull counts.
Moreover, none of that is opinion. Four dated numbers decide here. Each comes from a published record I can hand to a lender, not from a fuel’s image. My methanol vs lng marine fuel test stays narrow: what the vessel stores, what it buys, what the rule charges.
What this means for you: I do not rank the fuels by preference. I put four dated numbers in front of the file and let the vessel design, the route and the compliance position decide.
What each fuel stores, and at which temperature
The Methanol Institute’s 2023 marine fuel report gives lower heating value and volumetric energy density for each fuel. Marine gas oil reads 42.7 MJ/kg and 36.6 GJ/m3, LNG 50 MJ/kg and 23.4 GJ/m3, methanol 19.9 MJ/kg and 15.8 GJ/m3, liquid ammonia 18.6 MJ/kg and 12.7 GJ/m3, and liquid hydrogen 120 MJ/kg and 8.5 GJ/m3. Meanwhile, storage follows the same split. Marine gas oil and methanol sit at 20 degrees Celsius, LNG at minus 162 degrees, liquid ammonia at minus 34 degrees and liquid hydrogen at minus 253 degrees.
The volume cost, from the May 2023 figures, is concrete. Fuel and storage tanks on a methanol ship take about 2.4 times the space of a marine gas oil ship. More frequent bunkering and conventional tanks, including ballasts and no cryogenics, soften that penalty. Moreover, once tanks, secondary barriers and cofferdams are counted, methanol still holds more energy per cubic metre than LNG, ammonia or hydrogen. In May 2023 methanol engines had reached high technological maturity and builders sold them commercially, while methanol combustion cut particulates and black carbon by 95 percent. Specifically, the water side was explicit. Methanol turns toxic to aquatic organisms above 1,000 mg/l and especially above 10,000 mg/l, with a fish lethal concentration of 15,400 mg/l against 79 mg/l for heavy fuel oil and 0.068 mg/l for ammonia.
The marine fuel offtake structures page is where tank volume turns into a delivery schedule.
What this means for you: I price the tank volume into cargo intake before I compare fuel prices, because the space given up is paid in freight, not in dollars per tonne.
What the orderbook says
DNV’s annual 2025 data record 275 alternative-fuel orders, down 47 percent. That sits inside a total market of 2,403 orders against 4,405 in 2024, with alternative fuels holding 38 percent of gross tonnage. LNG took 188 orders in 2025 for 31 percent of total gross tonnage and methanol took 61, against 149 in 2024. Meanwhile, container ships by tonnage stand at about 58 percent LNG, 36 percent conventional and 6 percent methanol. Also, they account for 49 percent of gross tonnage on order and 68 percent of alternative-fuel newbuilds placed in 2025. In addition, bunkering followed the same pattern. Twenty-two LNG bunker vessels joined the orderbook in 2025, next to new bunkering vessels able to supply methanol and biofuel.
The delivery line is separate: 59 methanol-fuelled ships were delivered in 2025 and 38 in the first half of 2026. I keep orders and deliveries apart in every file, because only the second number proves a fuel case has left the paper stage.
The methanol bunkering page covers the infrastructure those orders depend on.
What this means for you: I read the orderbook as a dated commitment signal. However, I read deliveries as the only evidence that a fuel is actually moving through ports.
What the fuel costs
Maritime Propulsion reports November 2026 Methanex contract prices for fossil methanol. Those read about 700 USD a tonne in Asia-Pacific, 625 USD a tonne in China and 875 EUR a tonne in Europe. Its e-methanol estimates run from 800 to 1,600 USD a tonne historically and from 1,600 to 2,400 USD a tonne in some 2026 estimates. Electrolysis, the splitting of water by electric current, needs about 9.5 to 10.5 MWh a tonne.
Compliance rules then set a ceiling on what a compliant buyer can justify. Under FuelEU Maritime the ceiling reads 1,193 EUR a tonne on average for bio-methanol from 2025 to 2050, and 1,335 EUR a tonne once the emissions trading system is included. For e-methanol it reads 2,238 EUR a tonne from 2025 to 2033 and 1,325 EUR a tonne from 2034 to 2050, or 2,364 and 1,475 EUR a tonne with that system included.
The FuelEU Maritime page is where that ceiling is set.
What this means for you: I never set a posted contract price beside a compliance ceiling as if they were the same instrument. One is a price sheet, and the other is a ceiling written by a rule.
What the rules add to the bill
The September 2024 economic analysis puts a non-compliance cost on fossil fuel of 39 EUR a tonne in 2025, 353 EUR a tonne in 2035 and 1,997 EUR a tonne in 2050. It also shows emissions trading coverage rising from 40 percent in 2024 to 100 percent in 2026. At an allowance price of 100 EUR that adds 321 EUR a tonne. Also, the analysis holds 100 EUR a tonne of CO2 constant from 2024 to 2050.
Therefore, scope decides who pays. Under FuelEU Maritime the rules apply to ships above 5,000 gross tonnage. The rules take 100 percent of the energy on voyages inside the European Union and 50 percent on voyages in or out. Coverage reached 70 percent of navigation emissions in 2025, and a renewable fuel sub-target of 2 percent applies from 2034. Moreover, from 2030 the trading system adds a steady 150 EUR a tonne to fuel price.
The IMO framework measures on another basis. It uses greenhouse gas intensity, the life-cycle intensity of a fuel in grams of CO2 equivalent per megajoule, across carbon dioxide, methane and nitrous oxide on a well-to-wake basis. Zero or near-zero fuels qualify at up to 19.0 gCO2eq/MJ, 80 percent below the current average of 93.3 gCO2eq/MJ. An independent certification scheme recognised by the Marine Environment Protection Committee verifies the numbers. A digital register tracks intensity and compliance status, the framework is not a global carbon tax, and flag, port and coastal states apply it. The net zero framework page carries that rule.
What this means for you: I add the fee trajectory to the fuel price for every year of the asset. A fuel that looks cheap at delivery can be the expensive option in 2035.
What bunkering and fleet reality do to the choice
Methanol is a liquid at ambient temperature and pressure, bunkered through conventional infrastructure. Singapore began issuing commercial methanol bunkering licences on 1 January 2026. In October 2026 a methanol dual-fuel ship took about 5,000 tonnes of certified bioethanol there as a direct substitute fuel in methanol engines. Specifically, a licence is permission to supply, not volume delivered. On the fleet side, the largest dual-fuel operator runs about 20 methanol-capable container ships, with 19 as its 2026 target. Buyers ordered eight dual-fuel methanol ships of 4,500 TEU in December 2025, for delivery from 2028 to 2029. LNG needs cryogenic bunkering, and 22 LNG bunker vessels joined the orderbook in 2025. The tank penalty, 2.4 times the marine gas oil volume in the May 2023 figures, is why a methanol vessel plans more frequent stems.
The green methanol explained page covers which methanol is being bunkered.
What this means for you: I check the port and the delivery date before I check the fuel label. In fact, a fuel the route cannot serve is not a fuel option at all.
The five questions I ask before I accept a fuel case
Specifically, five questions decide a fuel case for me at concept stage. Also, I ask them in this order because any one of them can end the file. I ask them of myself first, in the same order, before I put anything in front of a lender.
- Which fuel is the orderbook actually committing to, and since when?
- What tank volume does the vessel have to give up?
- Which published price sheet is the fuel cost built on?
- What non-compliance cost does regulation add over the life of the asset?
- Which bunkering port can serve the vessel on the required schedule?
What this means for you: I will not accept a fuel case that cannot answer all five in writing with a date attached. Every missing answer becomes a risk that someone else prices later.
How I would write the fuel comparison appendix for my own file
The appendix I keep is one page of four rows, and every row carries its own date.
- Tank row: methanol at 19.9 MJ/kg and 15.8 GJ/m3 stored at 20 degrees Celsius against LNG at 50 MJ/kg and 23.4 GJ/m3 stored at minus 162 degrees, as recorded in May 2023.
- Orderbook row: 188 LNG orders against 61 methanol orders in 2025.
- Price row: about 700 USD a tonne of fossil methanol in Asia-Pacific in November 2026.
- Rule row: 39 EUR a tonne of non-compliance cost on fossil fuel in 2025 against 1,997 EUR a tonne in 2050.
Also, any row I cannot date does not go in the file. The fuel label never appears without the number behind it.
What this means for you: I hand over four dated rows rather than a recommendation. Therefore, the owner chooses the fuel against the vessel, the route and the compliance position.
Sources
- Methanol Institute, May 2023.
- DNV, 2026.
- Maritime Propulsion, 3 November 2026.
- Methanol Institute, September 2024.
- International Maritime Organization, page consulted 16 November 2026.
Frequently asked questions
Which fuel has the stronger orderbook?
LNG: 188 orders in 2025 for 31 percent of total gross tonnage, while methanol fell to 61 orders from 149 in 2024. Both sit inside alternative fuels at 38 percent of gross tonnage in a market of 2,403 orders in 2025, and those are orders rather than deliveries: 59 methanol-fuelled ships were delivered in 2025 and 38 in the first half of 2026.
Why does methanol need more tank space?
Because its volumetric energy density is lower: 15.8 GJ/m3 against 23.4 GJ/m3 for LNG and 36.6 GJ/m3 for marine gas oil, as recorded in May 2023. Tanks therefore take about 2.4 times the space of a marine gas oil ship, in exchange for storing the fuel at 20 degrees Celsius instead of minus 162 degrees, in conventional tanks without cryogenics.
What does regulation add to the cost of each fuel?
On fossil fuel, a non-compliance cost of 39 EUR a tonne in 2025 rising to 353 EUR a tonne in 2035 and 1,997 EUR a tonne in 2050, plus 321 EUR a tonne when 100 percent of maritime emissions are covered by the trading system at an allowance price of 100 EUR. The fuel itself is priced at posted contract levels of about 700 USD a tonne for methanol in Asia-Pacific in November 2026, which is a price sheet rather than a price paid.
How do the two fuels differ at the bunkering interface?
Methanol is a liquid at ambient temperature, bunkered through conventional infrastructure, with commercial licences issued since 1 January 2026; LNG needs cryogenic bunkering, and 22 LNG bunker vessels were added to the orderbook in 2025. A methanol dual-fuel ship also took about 5,000 tonnes of certified bioethanol in Singapore in October 2026 as a substitute fuel.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at concept stage and want these four numbers applied to your vessel and your route, I work through them with you in a focused session: strategic partnerships sets out how I support owners, developers and lenders on fuel selection files.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.