Home » POME Biogas Feedstock: Supply and Contracts That Survive Due Diligence
POME Biogas Feedstock: Supply and Contracts That Survive Due Diligence
10 min read · Apr 11, 2026 · By Alex
To contract palm oil mill effluent, the wastewater a mill drops after the fruit is sterilised and pressed, you contract the mill: the liquid is metered inside it, and biogas, the methane and carbon dioxide mixture, is counted in the digester beside it. The stream is strong on paper, at about 2.5 to 3.0 m3 of effluent per tonne of crude palm oil in 2026 data, giving 28-34 m3 of biogas per m3 at 54 to 65 percent methane, while gas capture, taking that methane off the liquid, is partial: around 130 of 450 Malaysian mills at the end of 2020 and less than a tenth of 850 Indonesian mills in 2019. A pome biogas agreement lives or dies on volume evidence, quality limits, collection terms and what happens when support expires, and I read it against the biogas, biomethane and biofuels industry branch.
First the stream and the plant, then what is actually captured today, how concentrated supply is, and what the offtake side must not assume. After that I lay out the five checks I run before signature and how I would write the case in a credit paper.
In short
- Stream: about 2.5 to 3.0 m3 of effluent per tonne of crude palm oil in 2026 data, giving 28-34 m3 of biogas per m3 at 54 to 65 percent methane.
- Plant: 70 to 95 percent of total biogas cost goes into installing the digester, in 2020 data, and the rest covers collection and processing.
- Capture: around 130 of 450 Malaysian mills at the end of 2020, and less than a tenth of 850 Indonesian mills in 2019.
- Checks: metered volume, chemical oxygen demand limits, site access, ownership of gas and digestate, and a price mechanism that outlives support.
- Credit paper: four dated rows, with targets, pilots and laboratory results kept out of the installed figures.
In this article
What you are actually contracting when you contract POME
The gas is made by anaerobic digestion, the breakdown of organic matter without oxygen, inside a digester that may stand on the mill side of the fence or on mine. The effluent is measured at the mill gate, in tonnes of fruit processed; the gas is counted at the digester inlet, so one document has to tie those two points together.
Ownership follows the same rule: who owns the captured gas, what it becomes as power or heat, and the digestate, the residue that leaves the digester as a soil fertiliser, must be written before money moves. I do not buy a nameplate figure, I buy metered flow tied to tonnage, because the mill can change flow, dilution and handling after signature. The agreement is a chain of evidence: meter, tonnage, quality limits, access, ownership, price.
What this means for you: name the meter, the tonnage basis, the digester inlet and the ownership of gas and digestate, so every cubic metre you pay for traces back to a tonne of fruit.
The stream itself
In 2026 data a mill yields about 2.5 to 3.0 m3 of effluent per tonne of crude palm oil, and each cubic metre gives 28-34 m3 of biogas at 54 to 65 percent methane. Chemical oxygen demand, the oxygen needed to oxidise all organic matter, runs from 15,000 to 100,000 mg/L and biochemical oxygen demand from 10,250 to 43,750 mg/L.
The 2026 review in the journal Biomass splits the fruit: on a fresh fruit bunch basis effluent carries about 50 to 75 percent and empty fruit bunches, the fibre left after stripping, about 20 to 30 percent, with 71 percent and 25.48 percent in a 60 tonnes per hour mill simulation. Co-digestion with empty fruit bunches lifted methane by 25 to 32 percent in 2026 tests, and other studies report biogas gains of about 20 to 40 percent.
Malaysia produced about 20.26 million tonnes of crude palm oil in 2025 on 5.7 million hectares; in 2026 data full effluent use is estimated at more than 500 MW. The methane share decides the offtake, so I keep how biomethane works beside the contract.
What this means for you: fix the chemical oxygen demand limits and the empty fruit bunch ratio in the agreement, since both move the yield.
From effluent to gas
The IEA biogas and biomethane outlook published in 2020 holds centralised digesters between 30 and 45 degrees C, with feedstock moved continuously, which is why their capital and operating cost per unit of energy sits above household scale.
In that same 2020 outlook, 70 to 95 percent of the total cost of biogas goes into installing the biodigesters and the rest covers collection and processing of the feedstock. Production cost runs between USD 2/MBtu and USD 20/MBtu, with Southeast Asia at USD 9/MBtu.
Converting a wastewater treatment plant averages around USD 15/MBtu in 2020 data and needs more than 5 000 m3 per day to be worth doing. Biogas is produced and consumed locally, so transport cost is negligible; what matters is the stages of biogas production between pond and plant. I check daily flow against digester cost, not against the gas price.
What this means for you: budget the digester first, since it carries 70 to 95 percent of total cost, and confirm the daily flow clears 5 000 m3 per day before you price anything else.
What is actually captured today
The 2020 policy brief from the Energy Studies Institute at the National University of Singapore counts around 130 of 450 Malaysian mills with capture at the end of 2020, about 28 percent, and 135 of 451 in the 2021 assessment, about 30 percent, against roughly 55 in the early 2010s.
In the 2021 evaluation those installations carry about 168 MW against a national potential near 508 MW and avoid about 4.96 million tonnes of CO2 equivalent a year; in 2016, 92 of 450 mills had biogas facilities. In Indonesia less than a tenth of 850 mills had capture in 2019, and full capture there would avoid about 41 million tonnes of CO2 equivalent. Malaysia and Indonesia together supply nearly 90 percent of the global palm oil offer, in 2020 data.
Registered biogas projects in the region were 53 percent of the global total under the clean development mechanism in 2020, and high capital and operating cost kept capture unattractive until incentives arrived in the 2000s.
What this means for you: check whether your mill sits among those without capture, and set the local case against biogas power plants across Southeast Asia.
Concentration and collection radius
The IEA Bioenergy Task 37 country report of September 2024 counts more than 100,000 biogas plants in China, with annual production near 81 TWh, and more than 10,000 in Germany, near 87 TWh.
Collection radius is the distance a plant can draw feedstock before the haul cost eats the gate price. One Danish plant takes agricultural substrates from 70 farms inside a 30 km radius and returns biofertiliser to those farms.
The United Kingdom reached 103,174 m3/h of biomethane capacity in 2022, and France runs 364 upgrading units, the highest reported count in 2024. The report groups plants by wastewater, organic waste, agricultural, industrial and landfill feedstock, and country comparison is complicated by different collection methods and units. In most countries biogas production has depended on investment support or subsidies to be financially viable, a finding published in 2024; I read it through the Malaysian feed-in tariff.
What this means for you: measure the collection radius of your mills in kilometres, because every extra kilometre is paid once in haul and once in lost gas.
What the offtake side must not assume
The IRENA cost review published in 2025 puts the levelised cost of bioenergy electricity at USD 0.087/kWh in 2024, 19 percent above the 2023 value of USD 0.073/kWh, and names feedstock price volatility and logistics costs as the cause.
Residues already sitting at an industrial processing site carry minimal or zero marginal cost in 2024 data; effluent that has to be trucked does not. Plant size is a trade-off between economies of scale and collection distance, because feedstock gets dearer as the average supply distance grows.
Variable operation and maintenance costs average around USD 0.004/kWh in 2024. Feedstock can also carry a charge: gate fees reach USD 100/tonne in some regions, or the cost turns negative when the producer must pay to dispose of it, in 2020 data. Bankable, meaning a case a lender can test against published data, is built in that row, so I check what makes biomethane bankable in Southeast Asia.
What this means for you: price collection distance and the gate fee in the same row as the offtake, because a cheap stream far away is not a cheap stream.
What I would test before I sign a POME agreement
I write five checks before signature, and I expect each one answered with a document rather than a number.
- Volume: measured effluent volume per tonne of palm oil, from meters the mill already keeps, never a nameplate figure.
- Quality: chemical oxygen demand limits and a stated consequence when the liquid falls outside them.
- Ownership: who owns the captured gas and the digestate, at the digester outlet and after it.
- Access: collection and site access terms, since a covered lagoon needs about 4 to 5 ha against 0.8 ha for an enclosed system, in 2026 data.
- Support: what the agreement says when the tariff or the carbon price goes, which is what the carbon price collapse of 2012 did to regional projects.
I mark any item the mill cannot evidence as uncontracted volume, and I price the project on what is left.
What this means for you: get all five answers in writing before the studies are spent, because each one changes either the volume you can book or the cost you can defend.
How I would write the POME supply case in a credit paper
I would show four dated rows in front of a lender, nothing more.
- Yield, 2026 review: 28-34 m3 of biogas per m3 of effluent at 54 to 65 percent methane.
- Capture, 2020 policy brief: 92 of 450 mills with biogas facilities in 2016.
- Capacity, 2026 review: about 168 MW installed against a 508 MW potential.
- Cost signal, 2024 cost data: USD 0.087/kWh in 2024.
Each row carries its year and its status: installed, estimated, simulated or reported. No target, no pilot and no laboratory number enters the table as an operating figure. Around those rows I would put the terms that make them real: meter basis, chemical oxygen demand limits, site access, ownership of gas and digestate, and the price mechanism after support ends.
What this means for you: write the four rows with their dates, mark estimates as estimates, and let the reader see which figure is installed and which is still only potential.
Sources
- IEA, Outlook for biogas and biomethane, 2020.
- IRENA, Renewable power generation costs in 2024, 2025.
- Energy Studies Institute, Producing Biogas from Palm Oil Mill Effluent in Southeast Asia, 2020.
- MDPI Biomass, Biogas Recovery from Palm Oil Mill Effluent in Malaysia, 2026.
- IEA Bioenergy Task 37, A perspective on the state of the biogas industry in 12 member countries, 2024.
Frequently asked questions
How much biogas can POME produce?
About 28-34 m3 of biogas per m3 of effluent at 54 to 65 percent methane, on effluent of about 2.5 to 3.0 m3 per tonne of crude palm oil, in 2026 data. The range moves with the concentration of the liquid and with whether empty fruit bunches are fed in alongside it.
Should a POME project rely on carbon credits?
Only as a secondary line. Registered biogas projects in Southeast Asia were 53 percent of the global clean development mechanism total, but the carbon price collapse of 2012 stopped projects that depended on those revenues and put companies into financial difficulty, so the model has to stand without them.
What makes a POME supply contract bankable?
A contract that ties measured volume, chemical oxygen demand limits, site access, ownership of the captured gas and digestate, and a price mechanism that survives the end of the tariff, because capture reached only about 28 percent of Malaysian mills at the end of 2020. A bankable paper shows which figure is installed and which is only potential.
Is co-digestion with empty fruit bunches worth it?
Yes in the reported tests: in 2026 co-digestion lifted methane by 25 to 32 percent against empty fruit bunch mono-digestion in specific conditions, and other studies report biogas gains of about 20 to 40 percent depending on the mixing ratio and the pretreatment. Those are test conditions, so I treat the gain as upside rather than as base case.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want the mill list, the metering terms and the collection clauses drafted before the studies are spent, I take that on as feedstock supply support for pre-FID teams. Send the mill, the tonnage and the intended use of the gas.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.