Home » Public Funding for PtL Projects: What the Money Covers and What It Does Not
Public Funding for PtL Projects: What the Money Covers and What It Does Not
10 min read · Sep 13, 2025 · By Alex
The money a power-to-liquid project can actually get arrives in three shapes: a fixed premium per kilogram of certified hydrogen paid through competitive auctions, a non-repayable grant, and a guaranteed loan, and none of the three replaces the others because they cover different lines of the same budget. A fixed premium means a price paid on each verified unit of certified output rather than a payment on capital spending, a grant is money awarded that is never repaid, and a guaranteed loan is debt a public body backstops. The technology itself, power-to-liquid, means making liquid fuel from renewable hydrogen and captured CO2, and I read ptl public funding as a calendar of separate instruments rather than a single pool.
In what follows I walk through the three instruments, the calendar each one runs on, what the money is meant to de-risk in a first commercial build, and the budget line no public instrument covers, plus the order I follow before financial close.
In short
- Premium: a fixed EUR price per kilogram of certified hydrogen, won in competitive auction, paid on verified output only.
- Grant: non-repayable money covering up to 60 percent of a project’s relevant cost, 2023 call terms.
- Loan: guaranteed lending of up to 75 million EUR through a thematic facility, 2024 terms.
- Calendar: every call opens, closes, invites and signs on its own dates, and I work backwards from them.
- Gap: neither instrument pays for the equity and debt residual of the build.
In this article
What public money is actually on the table
None of the three shapes replaces another, because each is attached to a different proof point: certified output, eligible capital cost, or repayment ability. A first-of-a-kind project, meaning the first commercial implementation of technology demonstrated only at smaller scale, is the profile they target.
Funding from the European Hydrogen Bank, run by the European Commission, is awarded as a fixed premium in EUR per kilogram of verified and certified RFNBO hydrogen. Its third auction, held between 4 December 2025 and 19 February 2026, selected 13 projects for more than 1.2 billion EUR across 8 European Economic Area countries, expecting almost 1.1 GW of electrolyser capacity and more than 1.4 million tonnes of hydrogen over the first 10 years of operation. Selection is not operation: those 13 projects await grant agreements, not fuel production.
What this means for you: I split my budget into three columns on day one, because the premium touches revenue, the grant touches capital cost, and the residual still needs debt.
How the auctions are built
The first auction of the European Hydrogen Bank scheme, launched in November 2023 and closed in February 2024, awarded nearly 720 million EUR to 7 renewable hydrogen projects from 132 bids; 6 of 7 signed grant agreements in October 2024, and each project must start producing within 5 years, for a potential 1.52 million tonnes over the first 10 years.
The second auction closed on 20 February 2025 with 61 bids and invited 15 projects, of which 6 signed on 20 January 2026 for 270.6 million EUR covering 381.25 MW of electrolyser capacity.
Auctions-as-a-service, meaning national money delivered through the same competitive auction, adds volume: in November 2024 Spain, Lithuania and Austria announced more than 700 million EUR of national funds, and Spain plus Germany added 1.7 billion EUR of national funds for the third auction. I hold these rounds against the grants and incentives register.
What this means for you: I put auction dates and my own study schedule on one timeline, because a bid I cannot document by the closing date is a bid I lose.
What the multilateral side adds
A 2024 study from the European Investment Bank measured the size of the gap that auctions cannot close: more than 85 percent of the companies consulted reported investment requirements above 100 million EUR, almost 60 percent needed more than 500 million EUR of capital spending, and about 40 percent more than 1 billion EUR. The same study puts the investment needed in new production facilities for biofuels and e-fuels at more than 50 billion EUR by 2035, rising to between 200 and 300 billion EUR cumulatively once hydrogen production, carbon capture and renewable electricity are included.
Also in 2024, backed by risk guarantees, the bank offers thematic venture debt and project financing of up to 75 million EUR, with up to 1 billion EUR earmarked for thematic finance, and the study recommends raising that loan size to 200 to 300 million EUR. I compare those terms with development finance institutions before I fix the debt plan.
What this means for you: I size the debt request against that 75 million EUR ceiling of 2024 first, then split or phase what exceeds it.
What international public finance has delivered so far
The international side is smaller than the headline totals suggest. The IEA Global Hydrogen Review 2026 reports that international public finance for low-emissions hydrogen in emerging economies grew from a negligible level in 2022 to around 3.3 billion USD of cumulative commitments to governments by the first quarter of 2026, while project-level international public finance reached around 650 million USD cumulatively by the same date, mainly for project preparation and reducing financing costs. Preparation money is the kind I can use before financial close, because it pays for the studies that make the rest of the stack possible.
Venture capital is a separate flow in the same 2026 review: hydrogen’s share of energy venture capital fell from a 13 percent peak in 2023 to 4 percent in 2025, with aviation taking almost 25 percent of hydrogen venture capital. I keep those flows apart; they answer different questions and they do not add up.
What this means for you: I treat public money in emerging economies and venture capital as context for my investors, not as lines in my own funding plan.
What the mandate does to a subsidy case
A quota changes what I can sell. The IATA ReFuelEU Aviation Handbook of September 2024 sets the minimum sustainable aviation fuel share delivered at 2 percent in 2025, 6 percent in 2030, 20 percent in 2035, 34 percent in 2040, 42 percent in 2045 and 70 percent in 2050, with the synthetic sub-share averaging 1.2 percent over 2030 to 2031 and reaching 35 percent from 2050.
Because there is no buy-out for fuel suppliers, a shortfall is owed again in the next reporting period, which turns the quota into contracted demand rather than a fine. Contracted demand only becomes revenue through an offtake, meaning a contract in which a buyer commits to take the fuel. The synthetic sub-share is the part I track most closely, because it is the slice a synthetic fuel plant can serve. I read the quota path on the ReFuelEU aviation page against my own delivery dates.
What this means for you: I price my project on the synthetic sub-share path, because that is the slice a power-to-liquid plant can win and the slice a shortfall must repay.
What regulatory risk does to a funding plan
The rules behind the premium are themselves in motion. Stibbe notes that the additionality delegated regulation applies to producers inside the European Union and to third-country producers exporting renewable hydrogen to it, so the same three criteria of additionality, temporal correlation and geographical correlation travel with the export case. An export case therefore needs the same evidence as a domestic one, and I prepare it before I bid.
A joint letter from the energy ministries of four member states and one state secretary in late March 2026 reported delayed investment decisions, projects stuck or cancelled, and long-term offtake failing to materialise despite national and European funding support and binding quotas. On 22 April 2026 the EU executive confirmed a targeted review for the second quarter of 2026. That is the risk I price when I set out investing in a power-to-liquid project before financial close.
What this means for you: I write a rule-change scenario into the funding plan, with dates for the review and for my own grant milestones, instead of assuming the rules hold as written.
How I sequence the stack
The November 2023 Innovation Fund call, described in the same 2024 European Investment Bank study, carried a budget of 4 billion EUR and, for the first time, a middle tranche for projects with capital expenditure of 20 to 100 million EUR, with non-repayable grants covering up to 60 percent of a project’s relevant cost; the European Innovation Council works with a 10 billion EUR budget combining grants of 2.5 to 4 million EUR with equity of up to 15 million EUR.
The IEA e-fuels report of 2023 uses a 5 percent cost of capital over a 25 year economic life and shows that the levelised cost of e-fuels climbs fast below a 40 percent electrolyser load factor, so a subsidy that ignores the load factor pays for a plant that runs less than assumed. I apply the sequence in how to finance a hydrogen project:
- Premium: pays the margin on verified certified output over the production period.
- Grant: pays eligible capital and operating cost, up to 60 percent of relevant cost under the 2023 call.
- Neither: pays the equity and debt residual, the site works, or an overrun after certification.
What this means for you: I apply for the instrument that matches the line item I am short on, and I read the load factor before I celebrate any subsidy.
The order I work in
- Instrument first: I apply to the auction premium first, because it is paid per kilogram of certified output and does not depend on how much capital I raise.
- Calendar: I set the call dates of 2026 against my own study schedule and work backwards from the closing date.
- Coverage: I check the share of capital spending the instrument can cover, up to 60 percent of relevant cost under the 2023 call.
- Residual: whatever remains has to come from equity and debt, and I size both before I send an application.
The sequence is short: I commission a feasibility study, meaning the technical and financial work that proves a project can be built and funded, then I match the study output to the call criteria, then I submit and wait for the signature that turns an application into a grant agreement.
What this means for you: I do not send an application before my study can answer the call criteria, and I do not count money as secured until the grant agreement is signed, and an invitation to negotiate is not a signature.
Sources
- IEA, The Role of E-fuels in Decarbonising Transport https://iea.blob.core.windows.net/assets/9e0c82d4-06d2-496b-9542-f184ba803645/TheRoleofE-fuelsinDecarbonisingTransport.pdf, 2023.
- Stibbe, Renewable hydrogen in the EU: a framework under pressure https://www.stibbe.com/publications-and-insights/renewable-hydrogen-in-the-eu-a-framework-under-pressure.
- IATA, ReFuelEU Aviation Handbook https://www.iata.org/contentassets/d13875e9ed784f75bac90f000760e998/refuel-eu-aviation-handbook.pdf, September 2024.
- IEA, Global Hydrogen Review 2026, Investment and innovation https://www.iea.org/reports/global-hydrogen-review-2026/investment-and-innovation, 2026.
- European Commission, European Hydrogen Bank https://energy.ec.europa.eu/topics/eus-energy-system/hydrogen/european-hydrogen-bank_en.
- European Investment Bank, Financing sustainable liquid fuel projects in Europe: Identifying barriers and overcoming them https://www.eib.org/attachments/lucalli/20240101_financing_sustainable_liquid_fuel_projects_in_europe_en.pdf, May 2024.
Frequently asked questions
What kinds of public funding can a power-to-liquid project actually get?
Three forms, each with its own logic: a fixed premium in EUR per kilogram of certified hydrogen paid through competitive auctions, non-repayable grants that can cover up to 60 percent of a project’s relevant cost, and guaranteed lending of up to 75 million EUR through a thematic facility, in terms published in 2024 and auctions that ran into 2026.
How much of the capital can a grant cover?
Up to 60 percent of the relevant cost under the call opened in November 2023 with a 4 billion EUR budget and a middle tranche for capital expenditure of 20 to 100 million EUR, while more than 85 percent of the companies consulted still needed more than 100 million EUR of capital spending in 2024.
Does a subsidy replace an offtake contract?
No: a premium or a grant improves the economics, but a shortfall against a minimum share is still owed in the next reporting period because there is no buy-out, so the contracted demand has to exist as well, under the rules set in 2024.
When should a developer start the funding process?
Before the study is finished: installations in operation before 1 January 2028 keep the additionality exemption only until 1 January 2038, and the third auction ran from 4 December 2025 to 19 February 2026 with grant agreements expected in the last quarter of 2026.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want a second read on your own sequence, my grants and incentives support covers the instruments, the calendars and the evidence each call requires, so you can check your funding plan line by line before the next deadline.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.