RFNBO Additionality and Correlation Rules: Answering Them Before an Auditor Asks

10 min read  ·  Sep 20, 2025  ·  By Alex

rfnbo additionality and correlation

Sourcing the electricity for a power-to-liquid plant is the first thing an auditor asks. From the branch page on power-to-liquid I answer directly: I sign a power purchase agreement, which is a contract for generation from a named renewable installation, and that installation must be new, commissioned no more than 36 months before my electrolyser and free of operating or investment aid. I match production to generation by calendar month until 31 December 2029 and by hour from 1 January 2030, and that is the rfnbo additionality rule, meaning genuinely new electricity, plus its two correlation rules. Those conditions and dates are the whole answer I owe before the detail starts.

I walk through the three criteria one at a time, then the calendar they run on, then what the move to hourly matching costs, and finally the evidence I assemble so my answers can be checked against my meter data.

In short

  • Additionality: I use new renewable capacity commissioned within 36 months before my electrolyser and free of operating or investment aid.
  • Temporal correlation: I match by calendar month until 31 December 2029 and by hour from 1 January 2030.
  • Geographical correlation: I keep the renewable installation beside my electrolyser, in the same price area or a connected one.
  • Cost: The move from monthly to hourly drives nearly 22 EUR per MWh of the increase in my hydrogen cost, in a 2025 system estimate.
  • Evidence: My metering, generation records and certification decide whether I get paid.
Facebook
Twitter
LinkedIn

In this article

The three criteria, and when they bite

A renewable fuel of non-biological origin is hydrogen, or a fuel made from it plus captured CO2, counted as renewable. Additionality means my electricity is new demand rather than power taken from someone else. Temporal correlation means matching production to generation in time, geographical correlation means where the two sit, and a bidding zone is the single price area I buy in.

Which pathway I claim decides how much I have to prove. The hierarchy for 2026, as Stibbe sets it out: grid electricity counts as fully renewable in a bidding zone whose renewable share exceeded 90 percent in the previous calendar year, or below 18 gCO2eq per megajoule with a power purchase agreement, or in an imbalance settlement period when renewables were curtailed and my production followed. Only when none of those applies do all three criteria apply together, which is what an auditor asks me to evidence.

What this means for you: I establish which pathway my grid supply falls under before I negotiate anything, because a bidding zone that clears those thresholds takes the three criteria off my desk for that route.

Additionality: what has to be new

Additionality is a date test and a funding test at once. The renewable installation I contract for must be commissioned within 36 months before my electrolyser, and it must not have received public funding. The European Hydrogen Observatory states the transition: installations operational before the end of 2027 follow the additionality rules only from 1 January 2038, while installations coming into service after 2027 must comply immediately. I read that as a transitional route with a fixed start date, never as a permanent exemption. Two dates drive my plan, one for each installation.

The RFNBO criteria page carries the wording I quote back. Physically, the renewable installation either stays off the grid or, if it is connected, carries a smart meter that proves no grid electricity entered my renewable fuel production, so my meter data answers the question on its own and I keep it first in the folder.

What this means for you: I date both installations in my feasibility file and check the funding history early, because a renewable installation commissioned more than 36 months ahead of my electrolyser fails the test outright.

Temporal correlation: month first, then hour

Temporal correlation is a calendar problem before it is an engineering one. Until 31 December 2029 my fuel must be produced within the same calendar month as the renewable electricity generated under my power purchase agreement, or charged into storage at the same connection point in that month. From 1 January 2030 the condition tightens to the same one hour period, and member states may bring that forward to 1 July 2027 after notifying the Commission. The delegated act analysis on emissions-euets.com sets out that calendar.

Under the rules for 2026, one price condition survives every date: any hour counts when the day-ahead price in my bidding zone is 20 EUR per MWh or lower, or below 36 percent of the current carbon price per tonne of CO2, so I can prove compliance from market data alone. I keep that hourly price series with the carbon intensity records an auditor reviews.

What this means for you: I build my production schedule against a month-level grid until 2029 and against an hour-level grid from 2030, and I budget for the member state bringing the hourly rule forward.

Geography, and what the grid connection allows

For 2026 the siting rule is simple to state. My renewable installation must sit in the same bidding zone as my electrolyser, or in an interconnected zone where day-ahead prices are at least as high, or in an offshore zone connected to it. A direct connection to a renewable installation is allowed as well, and I may mix a power purchase agreement with grid electricity so the electrolyser keeps running toward my offtaker’s profile rather than stopping whenever the contract volume runs out.

The cost of that flexibility shows up after 2030. A June 2025 power system study warned that hourly matching restricts when electricity can be used for hydrogen production and can reduce the ability of electrolysers to provide demand response, so a site chosen only for its day-ahead price may be a site chosen for the wrong hours.

What this means for you: I confirm the interconnection and day-ahead price relationship in writing before I site the plant, because geography is the rule I can change with a drawing rather than a contract.

What the switch to hourly matching costs

A study from October 2025, cited in the emissions-euets.com analysis, estimates that applying the full criteria with hourly matching raises average hydrogen costs across Europe by about 10 EUR per MWh at system level, that hourly matching alone is associated with a rise of just under 30 EUR per MWh in the levelised cost of hydrogen, which is the average cost per unit of output over a plant’s life, and that moving from monthly to hourly accounts for nearly 22 EUR per MWh of that.

In the same October 2025 estimate, selling surplus renewable electricity to the market trims electricity costs by about 5 EUR per MWh, and where there is no battery or hydrogen storage and a baseload profile is required the increase is larger. My hydrogen cost model carries both assumptions explicitly, and I state which profile I design to before any lender asks.

What this means for you: I price the plant twice, once at monthly matching for the years before 2030 and once at hourly matching after it, and I quote my own project cost rather than a system average.

What the market asks you to prove

The European Hydrogen Bank pays a fixed premium in EUR per kilogram of verified and certified renewable hydrogen, so the certification trail is the payment trigger rather than a supporting document. Its third auction, closed on 19 February 2026, selected 13 projects for more than 1.2 billion EUR, expecting more than 1.4 million tonnes of hydrogen over their first 10 years, with grant agreements expected in the last quarter of 2026, which sets the date my own paperwork has to be ready.

Demand sits in the same place the rules do. In the IEA Global Hydrogen Review 2026, more than 85 percent of investment targets existing hydrogen uses in industry and refineries or hydrogen-based fuels, and synthetic hydrocarbons are only now moving to first-of-a-kind projects, more slowly than modular transport uses. My investment file therefore has to answer both facts at once, before a lender asks.

What this means for you: I build the certification trail at the same time as the power purchase agreement, because in a premium-paying market the certificate, not the molecule, is what a counterparty buys.

What this means for the plant I design

The rules sit on top of an operating window I cannot move. In the IEA e-fuels report of 2023, the levelised cost of e-fuels rises very quickly once the electrolyser load factor drops below 40 percent, large-scale commercial electrolysers run at 65 to 70 percent efficiency on a lower heating value basis, and at the best sites renewable capacity factors can exceed 50 percent. Hourly matching tells me how much of that window I am allowed to use.

Delivery works the same way on the fuel side. In the IATA ReFuelEU Aviation Handbook of September 2024, the synthetic aviation fuel share averages 1.2 percent across 2030 to 2031 and reaches 35 percent from 2050, and a missed share is owed again in the next reporting period. So the delivery profile I promise has to be one the matching rule can actually produce, and my scale-up plan is written to that constraint.

What this means for you: I choose the load factor first and let the matching rule choose the hours, because a plant designed for the wrong hours pays the penalty twice, in cost and in delivery.

The order I work in

  • Pathway first: I document which supply route I take for 2026, because that decides whether all three criteria apply together or a single threshold carries the route.
  • Power purchase agreement second: I sign against renewable capacity commissioned within 36 months before my electrolyser, with no public funding behind it, and I record the commissioning date of both installations.
  • Calendar third: I plan against calendar month matching for 2029 and hourly matching for 2030, and I treat 1 July 2027 as a date a member state may move.
  • Evidence pack fourth: I keep metering, generation and certification records ready for an auditor from day one, in the order an auditor reads them.

What this means for you: I assemble the file in that order, from feasibility to signature, so nothing is signed before the evidence behind it exists. When the pack is complete, whoever asks gets the same answer in the same sequence.

Sources

Frequently asked questions

Additionality, temporal correlation and geographical correlation, and they apply together only when none of the simpler pathways applies, namely a bidding zone above 90 percent renewable share, an emission intensity below 18 gCO2eq per megajoule with a power purchase agreement, or an imbalance settlement period with curtailment (2026).

From 1 January 2030, when my production must fall within the same hour as renewable generation, with member states free to bring it forward to 1 July 2027 after notifying the Commission. Until 31 December 2029 the match is by calendar month (2026).

Yes, through the transitional route: installations operational before the end of 2027 follow the additionality rules only from 1 January 2038, while those coming into service after 2027 must comply from the first day. When the rules do apply, the renewable installation must still be commissioned within 36 months of the electrolyser and without public funding (2026).

An October 2025 study estimates about 10 EUR per MWh on average hydrogen costs across Europe with full criteria and hourly matching, with the move from monthly to hourly accounting for nearly 22 EUR per MWh of the levelised cost increase. The rise is larger where there is no storage and a baseload profile is required (2025).

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want the whole trail built before an auditor asks for it, I offer EU compliance and carbon intensity support for projects that need the electricity sourcing answer written down, checked against meter data and ready for a lender’s review.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.