Hydrogen Storage and Transport: How the Molecule Reaches the Buyer
10 min read · Sep 2, 2025 · By Alex
A project does not fail because the molecule cannot be made. It fails because green hydrogen never reaches the buyer at a price the buyer accepts. What changes along the way is the form, and the form decides who pays. In hydrogen storage and transport the choice is between moving the gas in a pipeline and converting it into ammonia or an organic carrier. A pipeline works when the distance is short and the route exists. A carrier covers the rest. Storage sits between geological caverns for long volumes and tanks for short buffers. The chain charges every conversion step twice, once on the way out and once on the way back. I therefore price the chain per kilogram delivered.
What this article covers
This article orders the options: how distance picks the route, what the carriers cost at the end of the chain. Then what the region is actually building and where the firm capacity sits. In addition, the planned capacity split, and the lines I write for a lender. Four pages I would normally link are still in draft. They cover pipelines and blending, liquid hydrogen and carriers, export to Japan and Korea, and storage solutions. I name them in words instead.
In short
- Distance: Below 1 500 km the pipeline is cheapest; above it a carrier is likely to win (2019).
- Conversion: The step into a carrier and the step back are both charged, so conversion is never free transport (2019).
- Shipping penalty: Above 10 kWh per kg of H2, more than 30 percent of the energy content (2026).
- Storage: Salt caverns under 0.6 USD per kg of H2 for long volumes, tanks for buffers (2019).
- Firm share: Only 9 percent of the announced 40 000 km of pipelines is operational or has committed investment (2026).
In this article
What storage and transport mean for a hydrogen project
The molecule at both ends is identical; what changes is its form, and each form is a carrier, the state chosen so hydrogen can be moved or held. Liquefaction cools hydrogen into a liquid that fits a ship tank. Ammonia cracking releases hydrogen from ammonia again. Reconversion turns a carrier back into hydrogen. A liquid organic hydrogen carrier holds hydrogen chemically and gives it back later.
Storage splits in two. A salt cavern is a void mined in rock salt, for large volumes held a long time, while buffer storage absorbs the short swings between production. In addition, demand. Load factor is the share of the year an asset runs. Pipeline repurposing converts an existing gas line instead of building a new one. Delivered cost is the price at the buyer’s gate.
The molecule does not change, the form does. In addition, every form is charged twice, once on the way out and once on the way back.
What this means for you: fix the form, the storage and the load factor before you fix the price, because the buyer pays for the chain and not for the molecule.
Distance decides the route
Distance is the first number I write, because it picks the route. Moving hydrogen as a gas by pipeline costs around 1 USD per kg of H2 for about 1 500 km. That figure includes all capital and operating costs (2019). Converting it into ammonia costs around 1 USD per kg of H2. Transmitting ammonia over that distance costs around 1.5 USD per kg of H2 (2019). At 2 500 km the ammonia route, conversion included, reaches around 2 USD per kg of H2. It is then broadly similar to hydrogen gas (2019). The Future of Hydrogen sets the rule plainly: below 1 500 km the pipeline is the cheapest delivery option. Above 1 500 km, shipping as ammonia or an organic carrier is likely to cost less (2019).
Shipping overseas generally means liquefying the molecule or moving it as ammonia or an organic carrier (2019). The engineering maturity of each conversion step sits on my technology maturity and scale-up page.
What this means for you: fix the distance band before you fix the route, because the pipeline wins under 1 500 km. In addition, the carrier wins over it.
What the carriers cost at the end of the chain
The Global Hydrogen Review 2026 puts a number on that penalty: where pure hydrogen is required at the point of use, shipping implies a minimum cost of around 2 USD per kg of H2. In addition, energy use sits above 10 kWh per kg of H2, more than 30 percent of hydrogen’s energy content. That penalty comes from intensive liquefaction or reconversion steps such as ammonia cracking (2026). Announced hydrogen pipeline projects exceed 40 000 km by 2035. Only 9 percent of that length is operational or has a committed investment (2026). Around 170 ammonia and 130 methanol port terminals are in operation. Ammonia leads among announced projects, while more methanol infrastructure is under construction mainly for bunkering. Construction has also started in Japan on the first commercial-scale terminal for liquefied hydrogen imports (2026). The port side of ammonia sits on my green ammonia page.
What this means for you: charge the reconversion step separately in your model, because a shipping price is not a delivered price. In addition, the energy penalty sits with the buyer.
What Southeast Asia is actually building
The APERC Hydrogen Report 2024 records what the region is building. In November 2024 a joint development framework agreement set up a hydrogen pipeline connecting Sumatra, the Riau Islands and Singapore. Its capacity of 100 000 tonnes of hydrogen a year feeds a 600 MW hydrogen-ready gas turbine on Jurong Island. That complements a 340 MW open-cycle gas turbine announced in 2023 (2024). Regional committed production capacity reached 4.2 million tonnes per year in 2024, with state-owned enterprises playing a major role (2024). China hosts the largest share of renewable energy based hydrogen projects in the region. It committed 1.8 million tonnes per year as of 2024 (2024). The production side sits on my technology choices page for the region.
What this means for you: read that pipeline as an agreed framework and not as steel in the ground, and size your own storage around what is actually commissioned.
What I treat as firm and what I treat as a plan
Salt caverns typically cost less than 0.6 USD per kg of H2. They have served the chemical sector since the 1970s in one country and the 1980s in another (2019). Tanks, by contrast, reach discharge efficiencies of around 99 percent (2019). Announced underground storage could provide 11 TWh by 2035, or 335 kt of hydrogen. Just over 7 percent sits at final investment decision or in construction. That equals 0.6 percent of the throughput of committed projects (2026). Pipelines show the same split: 9 percent of the 40 000 km announced by 2035 is operational or carries committed investment (2026). Firm to me means sanctioned, built and contracted; everything else is a plan with a date attached.
What this means for you: put firm capacity on the balance sheet and planned capacity in a sensitivity, because an announced figure is not a service you can book.
Why the carrier route shows up in your model
The Global Hydrogen Review 2025 lists what still stands in the way. It names high production costs, demand and regulatory uncertainty, and infrastructure gaps (2025). Cumulative firm offtake agreements stand at less than 2 Mtpa, merely 5 percent of the potential production announced projects could achieve by 2030 (2025). In emerging economies capital costs can reach 15 percent, three times higher than in advanced economies. There, 80 percent of the projects are export-oriented (2025). A project that must export to earn cannot pick its carrier on engineering preference alone. The conversion cost enters the price the buyer sees, the reconversion enters it again. In addition, the route has to survive a buyer who prices the molecule at the gate. The same logic for fuels made from hydrogen sits on my power to liquid page.
What this means for you: if your revenue depends on an export market, choose the carrier that market already buys, not the one your flowsheet prefers.
What I put in front of the lender
The report Creating a global hydrogen market treats certification as an essential element of any trade. Certificates would carry compliance with standards and sustainability data such as carbon footprint and renewable energy content. Chain of custody would record how ownership transfers along the supply chain (2023). Also, the five critical elements of such a system are the scheme itself, the design of its standards, governance, control and verification, and tracking with a business model (2023). Eight voluntary and five mandatory schemes were assessed and none of the existing systems is suitable for cross-border trade (2023). I therefore write the certificate into the logistics plan rather than into the marketing page, because the cargo and its data travel together. The commercial framing of that package sits on my contracting and risk management page.
What this means for you: name the scheme your buyer accepts before you name the port, because an uncertified cargo is a molecule nobody can book.
The five lines I write in the logistics plan
By the time a logistics plan reaches a lender. The argument has to fit on one page, so I write five lines and defend each of them. First, the distance band that decides the route (2019). Second, the conversion cost charged twice, out and back (2019). Third, the shipping energy penalty above 10 kWh per kg (2026). Fourth, the committed share of the infrastructure you rely on (2026). Fifth, the certificate that travels with the cargo (2023).
Those five lines are one rule: the delivered cost is the only number your buyer recognises. In addition, every step you add has to be paid for twice. Nothing else survives a lender’s reading.
What this means for you: write the five lines, then defend the delivered cost, because that is the number the offtaker signs.
Sources
- IEA, The Future of Hydrogen https://iea.blob.core.windows.net/assets/9e3a3493-b9a6-4b7d-b499-7ca48e357561/The_Future_of_Hydrogen.pdf, 2019.
- Also, IEA, Global Hydrogen Review 2026, Trade and infrastructure https://www.iea.org/reports/global-hydrogen-review-2026/trade-and-infrastructure, 2026.
- Asia Pacific Energy Research Centre, APERC Hydrogen Report 2024 https://aperc.or.jp/file/2025/3/18/APERC_Hydrogen_Report_2024_final.pdf, 2025.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
- IRENA and RMI, Creating a global hydrogen market: Certification to enable trade https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2023/Jan/IRENA_Creating_a_global_hydrogen_market_2023.pdf, 2023.
Frequently asked questions
What is the cheapest way to move hydrogen?
As a gas by pipeline for about 1 500 km, where it costs around 1 USD per kg of H2 including capital and operating costs, and as ammonia or an organic carrier beyond that distance (2019). For shorter distances than that, distribution usually relies on trucks carrying gaseous or liquid hydrogen (2019).
Should I store hydrogen or convert it before shipping?
It depends on the distance: below 1 500 km the pipeline wins, above it the carrier wins, while storage stays in salt caverns below 0.6 USD per kg of H2 for the long volumes and in tanks for short buffers (2019). Geological storage suits large capacity and long duration, while tanks suit short and small needs (2019).
How much does shipping add to the cost of hydrogen?
Where pure hydrogen is needed at the point of use, shipping implies a minimum of around 2 USD per kg and an energy use above 10 kWh per kg, more than 30 percent of the energy content, because of liquefaction and reconversion (2026). The conversion step at export and the reconversion at import remain significant and are charged again at the buyer’s gate (2019).
What infrastructure is actually available in Southeast Asia?
Ports and pipelines are being built rather than finished: around 170 ammonia and 130 methanol terminals are in operation, only 9 percent of the announced 40 000 km of pipelines is operational or committed, and a pipeline of 100 000 tonnes of hydrogen per year was agreed in November 2024 to link Sumatra, the Riau Islands and Singapore (2024, 2026).
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want a second reading of the vector and the storage before your cost model is frozen, I offer technology maturity and scale-up support as a working session on the route, the carrier and the buffer, with the five lines written out and every assumption dated.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.