Home » Methanol vs Ammonia as Marine Fuel: Six Differences That Decide the Project
Methanol vs Ammonia as Marine Fuel: Six Differences That Decide the Project
10 min read · Nov 2, 2026 · By Alex
Methanol is a liquid at ambient temperature that burns in engines available commercially. The May 2023 figures put ammonia at 18.6 megajoules per kilogramme against 19.9 for methanol, and ammonia needs minus 34 degrees or pressure, and is lethal as a toxin at 0.5 percent in air, long before its flammable range of 15 to 28 percent. Methanol wins on availability; ammonia wins on carbon only if the molecule is green. For a project at concept stage, the methanol vs ammonia marine fuel choice is decided neither by energy nor by a published price: it is decided by the safety case and the supply contract behind the molecule. I set the whole comparison on the sustainable maritime fuels page and I repeat it here for a developer reading with an offtaker over the shoulder.
I score that choice on six differences, in the order in which they usually block a file: energy per unit, storage and temperature, toxicity, engine availability, what has been ordered, and what certification requires. Each one can stop a concept before the route earns anything.
In short
- Energy: On the May 2023 figures methanol gives 19.9 megajoules per kilogramme and 15.8 gigajoules per cubic metre against 18.6 and 12.7 for liquid ammonia, so volume rather than weight decides.
- Storage: Methanol stays liquid at 20 degrees Celsius and ordinary pressure, while the handbook of June 2023 keeps ammonia at minus 34 degrees or under pressure, expanding 850 times.
- Toxicity: Ammonia is a lethal toxin at 0.5 percent in air, below its flammable range of 15 to 28 percent, so the file needs a safety case, not a preference.
- Engines: Methanol engines were commercially available in May 2023, while the handbook of June 2023 expected ammonia engines two to three years later.
- Orders and certificate: In 2025 methanol took 61 orders against 149 in 2024, and the certificate, not the molecule, decides whether a file reads as green in 2026.
In this article
The short answer on one page
At concept stage I answer the fuel question in one line: choose the molecule you can store on the vessel, contract for the season, and certify in the file. Methanol is an ambient liquid that meets engines already on the market. Ammonia carries less energy in both units, needs refrigeration or pressure, and is a lethal gas long before it becomes a flammable one. The six differences below follow the order in which they block a file: energy per unit, storage and temperature, toxicity, engine availability, what has been ordered, and what certification requires. The first three shape the vessel, the fourth shapes the contract year, the fifth shows what the market has actually done, and the sixth decides whether the molecule reads as green. None of these sources publishes a price, so I keep price out of the comparison.
What this means for you: I treat each difference as a gate with a date attached, and I close them in this order, because a fuel that fails the storage gate or the safety gate never reaches the engine or the certificate.
Difference one: energy per kilogramme and per cubic metre
The report of May 2023 from the Methanol Institute gives the two numbers I use first. The lower heating value is the energy released when the water in the exhaust stays vapour, and the volumetric energy density is the energy held in a cubic metre of tank. On its May 2023 figures, methanol stands at 19.9 megajoules per kilogramme and 15.8 gigajoules per cubic metre, liquid ammonia at 18.6 and 12.7, marine gas oil at 42.7 and 36.6, and LNG at 50 and 23.4. The same report records that storage and fuel tanks on a methanol ship take about 2.4 times the space of marine gas oil tanks, cushioned by more frequent bunkering and by conventional tanks, including ballast tanks, with no cryogenics. The reading for a developer comparing green methanol with an ammonia route is plain: the two alternatives are close on weight, ammonia is worse on volume, so this is a storage and logistics contest rather than an energy contest.
What this means for you: I size the tank before I compare the fuels, in cubic metres of fuel and in tank volume, and I let the bunkering interval of the route follow from that number instead of from a preference for a molecule.
Difference two: ambient liquid against minus 34 degrees
Methanol is an ambient liquid, meaning it stays liquid at ordinary temperature and pressure; the report of May 2023 stores it at 20 degrees Celsius and records that this is why its transport, storage and bunkering are simpler than those of ammonia, hydrogen or LNG. The Green Shipping Programme handbook of June 2023 stores liquid ammonia at minus 34 degrees, or at 20 degrees under pressure, and records that it expands 850 times when it turns from liquid to gas, that a brief exposure at 5,000 ppm is lethal, and that one litre spilled can form 170 cubic metres of gas at that concentration. The shipyard consequence follows directly: a pressurised or refrigerated tank, a vapour return line, and a toxic area, which is the zone around the tank and the manifold where a leak could reach a harmful concentration.
What this means for you: I take the tank arrangement before the fuel choice, because a refrigerated or pressurised ammonia tank changes deck layout, crew access and safety distances, while methanol drops into conventional tanks and turns the berth into a methanol bunkering procedure I can write today.
Difference three: toxicity redesigns the ship
The handbook of June 2023 gives ammonia a flammable range of 15 to 28 percent in air, the lower flammability limit being the lowest concentration that can burn, and a minimum ignition energy, the smallest spark that starts a fire, of 40 to 170 millijoules, which is 150 times what methane needs. The green ammonia page carries the wider production and use picture this safety test sits inside. It self-ignites above 651 degrees Celsius, yet it is a lethal toxin at 0.5 percent in air, far below that range: toxicity is the key hazard, and harmful concentrations start at a fraction of one percent. The same handbook records that the safety principles used for LNG, segregation, double barriers and leak detection, can guide the design provided every leak scenario is controlled. Gas detection means fixed sensors and an alarm that isolate a space before entry.
The report of May 2023 adds the environmental side: the concentration lethal to half a fish population is 0.068 milligrams per litre for ammonia, against 15,400 for methanol and 79 for heavy fuel oil, and methanol combustion cuts particulates and black carbon by 95 percent. Neither figure settles the case. The first sets the gas detection and ventilation design, the second sets the spill response and the bunkering procedure.
What this means for you: I ask for the safety case and the accepting authority before I compare engines, because an ammonia file lives or dies on ventilation, gas detection and access rules, while a methanol file lives or dies on spill response at the berth.
Difference four: the engine you can order
The report of May 2023 records that methanol internal combustion engines have a high level of technological readiness and are commercially available, and IRENA’s 2021 pathway records that methanol can be used in engines built by well-known manufacturers. I keep those statements attached to their dates, because a maturity note written in 2023 describes the market of 2023.
The handbook of June 2023 records another position for ammonia: several engine makers were then working on ammonia combustion with engines expected two to three years later, effective international statutory rules for ammonia as fuel were not in place at that date, and class rules published by several societies in 2021 had not yet been tested by a newbuild. A class rule is not an international statutory rule, and I never let one stand in for the other in a file.
What this means for you: I separate two contract questions, which engine can I take for delivery with this ship, and which rules will the flag accept on delivery day, because only the first is answered by a maturity note written in 2023.
Difference five: what has actually been ordered
The annual orderbook figures published by DNV in 2026 for 2025 record 275 orders for alternative fuelled vessels, down 47 percent in a renewal market of 2,403 orders against 4,405 in 2024, with the alternative share holding at 38 percent of gross tonnage. LNG took 188 orders, or 31 percent of total gross tonnage; methanol fell to 61 orders from 149 in 2024; ammonia recorded limited uptake. In the container segment the 2025 split by tonnage is about 58 percent LNG, 36 percent conventional fuel and 6 percent methanol.
For this region the reading is direct. An orderbook is the only public evidence of demand, and ammonia demand is still mostly intention rather than steel in the water, which is why the ammonia offtake conversation in Southeast Asia belongs before the technology choice rather than after it.
What this means for you: I ask for the orderbook line of my fuel before a concept freeze, and I read limited uptake as a supply question first, because the vessel and the bunker port have to arrive on the same schedule as the engine.
Difference six: what certification requires
The framework’s FAQ from the International Maritime Organization defines greenhouse gas intensity as the grams of carbon dioxide equivalent released per megajoule of fuel energy, measured well-to-wake, from production to combustion in the engine, covering carbon dioxide, methane and nitrous oxide. On those figures, zero and near-zero fuels sit at 19.0 grams or less against a current average of 93.3 grams, which is 80 percent lower. The same FAQ requires that emissions and fuel sustainability be verified independently through a fuel certification scheme, meaning an independent scheme recognised by the committee that checks both the claimed intensity and the sustainability of the molecule.
That asymmetry decides the file. A green methanol molecule and a grey ammonia molecule look identical in the tank and differ only in the certificate that carries the intensity, and that certificate is what a lender discounts in a bankable fuel file.
What this means for you: I do not compare molecules, I compare certificates, and I ask which scheme verified the intensity, on which well-to-wake boundary, and whether the same verification still holds when the ship first calls on my route.
The choice I would write into the file
When I write the concept file I put four lines on the first page and I leave none of them blank. The fuel itself, methanol or ammonia, with the production route named. The certified greenhouse gas intensity of that molecule with the scheme that verified it well-to-wake, because the intensity of ammonia depends on how the hydrogen and the nitrogen were produced, and the intensity of methanol depends on where its carbon came from. The safety case with the authority that accepted it, covering tank arrangement, toxic area, gas detection and bunkering procedure. The supply contract with its first delivery date, because an intention is not a signed contract and an announced capacity is not an offer sold.
What this means for you: I sign nothing until those four lines carry a source and a date, and I keep the methanol vs ammonia marine fuel question open until the certificate, the accepted safety case and the first delivery are written on the same page.
Sources
- Methanol Institute, Marine Methanol: Future-Proof Shipping Fuel, May 2023.
- Green Shipping Programme, Ammonia as a Marine Fuel Safety Handbook, revision 02, 5 June 2023.
- DNV, LNG-fuelled container ships sustain alternative fuel share of global orderbook, consulted 17 November 2026.
- International Maritime Organization, The IMO Net-Zero Framework, FAQs, consulted 16 November 2026.
- IRENA, A pathway to decarbonise the shipping sector by 2050, 2021.
Frequently asked questions
Which fuel carries more energy, methanol or ammonia?
On the May 2023 figures, per kilogramme methanol carries 19.9 megajoules against 18.6 for liquid ammonia, and per cubic metre it carries 15.8 gigajoules against 12.7. Methanol therefore holds more energy in the same tank volume, and the difference is wider on volume than on weight, because ammonia has to be refrigerated or pressurised to stay liquid. For a tank designed in cubic metres, that gap shows up as deck space and as the number of bunkering calls the route can absorb.
Is ammonia a zero emission fuel?
It carries no carbon atom, but its greenhouse gas intensity depends on how the hydrogen and the nitrogen were produced, and the framework measures intensity well to wake, covering carbon dioxide, methane and nitrous oxide over the whole fuel cycle. An ammonia molecule therefore needs a certified intensity like any other fuel, and carrying no carbon in the molecule is not the same as showing a low intensity in the file. The certificate is what tells the two apart.
Can a methanol ship be converted to ammonia later?
Nothing in these sources describes a conversion from methanol to ammonia. The tank arrangement, the toxic area and the gas detection design all differ between the two fuels, so I treat an ammonia vessel as a new design rather than a retrofit, and I write a fresh safety case for it rather than assuming the existing one carries across. That is a design decision, not a preference, and I take it at concept stage rather than at delivery.
Which one is cheaper?
None of these sources gives a price for either fuel, so I do not quote one. The report of May 2023 gives energy density and the handbook of June 2023 gives safety properties, and a cost claim without a dated source is a claim I cannot defend in a project file. What I can defend is a dated comparison of energy per unit, storage, toxicity, engine availability, orders and certification, which is what this page sets out.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want this comparison run against your route, your bunkering port and your offtaker’s requirements, I take it through a working session with the file open, and you can start it through a strategic partnerships engagement.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.