Home » PtL Finance and FID: How a Power-to-Liquid Project Gets Funded
PtL Finance and FID: How a Power-to-Liquid Project Gets Funded
10 min read · Feb 2, 2026 · By Alex
Also, lenders fund a power-to-liquid project in layers, and each layer follows only once two conditions hold. Firm purchase agreements cumulate to less than 2 Mtpa. This is 5 percent of what announced projects could produce by 2030. In 2025 only 9 percent of announced projects worldwide had secured committed investment, that is capital actually secured rather than announced, against 0.5 percent in emerging economies where capital can reach 15 percent, three times the level of advanced economies. Also, those are the two numbers that a PtL finance and FID case has to answer. Power-to-liquid means fuel made from renewable electricity: an electrolyser splits water into hydrogen. Also, hydrogen combines with captured carbon dioxide to make a liquid fuel. Start from the power-to-liquid explainer for the process, here I take the money apart.
PtL Finance FID: Power-to-Liquid Project Gets Funded
I order this file in four steps: what is actually committed, what public money does first, what demand has to show. Also, what the asset has to earn. Each step carries one figure and one date, because a case that cannot date its own numbers is not a case.
In short
- Committed capital: in 2025, 9 percent of announced projects worldwide held committed investment and 0.5 percent in emerging economies.
- Firm demand: less than 2 Mtpa of firm purchase agreements, 5 percent of announced production for 2030.
- Public money first: 6.6 billion USD of development finance institution loans in 2021 to 2025 and 38 billion USD of public funding.
- Asset economics: in 2023 modelling, 25 to 35 USD per gigajoule at 50 USD per MWh, and a load factor below 40 percent that breaks the cost.
- My exclusions: an announced pipeline, an announced offtake, a comfortable cost of capital and a cheap equipment line, none of them financing.
In this article
What a power-to-liquid financing case has to answer
The case answers two questions before anything else: who is bound to buy the fuel, and who has already put capital into the file. Everything below follows from those two answers.
The vocabulary is narrow. The final investment decision is the point where the sponsor commits the capital and the plan stops being a plan. Committed investment is capital a project has secured, not capital announced. Firm offtake is a purchase agreement a buyer is bound by, not an expression of interest. A development finance institution is a public or multilateral lender that takes risk commercial lenders will not take yet. Equity is the sponsor’s own capital, and senior debt sits ahead of it in the repayment queue. The levelised cost spreads the investment over the fuel actually made.
What this means for you: put those seven definitions on the first page of your file. A lender who has to ask what committed investment means in your project will price that question into the debt.
What the money that is already committed looks like
The five key questions section of the 2025 review is where I open every file. It reported in 2025 that only 9 percent of announced projects worldwide have secured committed investment, against 0.5 percent in emerging economies, and that in those economies the cost of capital can reach 15 percent, three times the level of advanced economies. Firm purchase agreements cumulate to less than 2 Mtpa. This is 5 percent of what announced projects could produce by 2030.
The second finding decides where the money goes. In 2025 the electrolyser stack was only 15 to 20 percent of the installed investment. Therefore, the bulk of capital sits in balance of plant, construction and grid connection. A cheaper stack does not make a cheaper plant. The same hub from the investor’s side runs those numbers the other way round.
What this means for you: treat committed investment as your gate, not your ambition. Count what sits under secured capital and bound buyers first, then size the debt against what is left.
The public money that moves first
Public money prices the file before private money will look at it. The December 2025 Southeast Asia briefing recorded 6.6 billion USD of loans from development finance institutions in 2021 to 2025, 38 billion USD of public funding advanced in national policies since the previous review, and 8 billion USD invested in production in 2025. Those are the cheapest layers in the stack and they arrive first.
Regional demand runs at 4 Mt in 2024, split between Indonesia at 35 percent, Malaysia at 22 percent, Viet Nam at 15 percent and Singapore at 12 percent. Five regional countries now hold a national strategy. No certification scheme is yet in place, with work under way in three countries. The development finance institutions page sets out what a public lender will and will not cover.
What this means for you: treat public money as the layer that reduces risk rather than the layer that funds you. Where no national strategy and no certification path exist yet, the first question a lender asks is still open.
Demand decides whether debt can be raised
Offtake is the volume a buyer has agreed to take. Also, the December 2025 Southeast Asia briefing separates it into announced and firm. In 2021 to 2025 it counted 7 Mtpa of offtake announced globally of which only 1.6 Mtpa is firm, and 16.5 Mtpa of export projects to 2030 of which 4.2 Mtpa have a buyer identified. An announcement makes no contract.
Regionally, announced projects equal 12 percent of current regional demand. Meanwhile, only 6 percent of announced capacity has reached the final investment decision, both as counted in December 2025. A lender reads the listed barriers as repayment risk: high capital cost, low renewable penetration and weak fuel switching incentives. That is why offtake agreement structuring sits ahead of the debt model.
What this means for you: split your offtake column into firm and announced before you build any model. Size debt on announced volume and you size it on demand nobody signed.
What the asset itself has to earn
The 2023 e-fuels report gives the arithmetic I use. At 50 USD per MWh in that 2023 modelling the power price alone contributes 25 to 35 USD per gigajoule of fuel, or 1,000 to 1,500 USD per tonne of oil equivalent, before any investment or consumable. In the same 2023 modelling the levelised cost starts increasing very quickly once the load factor, the share of hours the plant runs, drops below 40 percent. That modelling assumes a 5 percent cost of capital over a 25 year economic life, with operating cost beyond electricity at 1.5 percent of capital for electrolysis and 3 percent for synthesis each year, and it pairs 30 and 50 USD per MWh with 800 and 2,000 USD per kilowatt of electrolyser.
The World Bank survey of February 2026 adds the financing consequence: less established technologies carry a higher financing cost unless it is mitigated by warranties, guarantees or other measures, and financing requirements can push a project towards established contractors and proven equipment, which is why the equipment choice is a financing decision. The structure that carries these cash flows sits in infrastructure project finance.
What this means for you: fix your load factor and your power price before you fix your equipment list. Both move the levelised cost more than any gain you negotiate on the stack.
What I will not treat as financed
Four exclusions, each with its own date.
An announced pipeline is not funding. The 2026 review puts the announced pipeline at 27 Mt to 2030, with committed and high-potential production falling from 10 Mt to just above 6 Mt, and 22 Mt at risk of losing its 2030 slot without an investment decision before early 2027.
An announced offtake is not revenue: 7 Mtpa announced against 1.6 Mtpa firm between 2021 and 2025, and below 2 Mtpa cumulative firm at 5 percent of announced 2030 production.
A cost of capital assumed at a comfortable level is not a financing plan: in 2025 the emerging economy level was 15 percent, three times advanced economies, with only 0.5 percent of announced projects there holding committed investment. A cheap equipment line is not a cheap plant: in 2025 the stack was 15 to 20 percent of the installed investment.
What this means for you: run your file through these four exclusions before you send it. Anything that fails one of them is a claim, and a claim does not service debt.
What this changes for a Southeast Asian project
A lender finances the same project under a harder regime. Regional demand was 4 Mt in 2024 with a production mix of ammonia at 49 percent, refining at 31 percent and methanol at 20 percent, and a potential of nearly 11 Mtpa below 6 USD/kg by 2030 that is not yet a business. In 2025 only 6 percent of announced regional capacity had reached the final investment decision.
In 2025, 80 percent of announced projects in emerging economies targeted exports, moving the credit question to a buyer abroad. The 2026 review’s infrastructure answer is to concentrate on industrial and port clusters where production and users sit together, because 22 Mt risks its 2030 slot without a decision before early 2027. The low carbon fuels investment page covers the equity that sits at the bottom of the stack.
What this means for you: put your project next to a user before you put it next to cheap power. In this region, a cluster is what turns an announced volume into one a bank will lend against.
The four lines I would put in front of a lender
Line one, demand: less than 2 Mtpa of firm purchase agreements, 5 percent of announced 2030 production, from the five key questions section of the 2025 review. The second line, capital: in 2025, 9 percent of announced projects held committed investment worldwide against 0.5 percent in emerging economies, where capital reaches 15 percent, three times advanced economies, same source.
The third line, public money: 6.6 billion USD of development finance institution loans in 2021 to 2025, 38 billion USD of public funding, and 8 billion USD invested in production in 2025. Line four, the asset: 25 to 35 USD per gigajoule at 50 USD per MWh and a 5 percent cost of capital over 25 years, both as modelled in 2023, with the stack at 15 to 20 percent of installed investment as reported in 2025.
What this means for you: send those four lines, each with its date, before you send the model. A lender who can date your demand, your capital, your public money and your asset will read the next page.
Sources
- IEA, Global Hydrogen Review 2026, Executive summary https://www.iea.org/reports/global-hydrogen-review-2026/executive-summary, 2026.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
- IEA, Global Hydrogen Review 2025, Southeast Asia, 9 December 2025 https://iea.blob.core.windows.net/assets/745a259b-9cb7-4e1d-9ba1-a8b63d1eaae8/GHR2025_SEA_Webinar.pdf, 2025.
- IEA, The Role of E-fuels in Decarbonising Transport https://iea.blob.core.windows.net/assets/9e0c82d4-06d2-496b-9542-f184ba803645/TheRoleofE-fuelsinDecarbonisingTransport.pdf, December 2023.
- World Bank, ESMAP, Electrolyzers for Hydrogen Production: Technical and Economic Characteristics https://documents1.worldbank.org/curated/en/099022326123011297/pdf/P506220-b45b0865-8706-4862-8792-d8cc71f84569.pdf, February 2026.
Frequently asked questions
How much of announced hydrogen production actually has firm offtake?
Less than 2 Mtpa cumulatively, which is 5 percent of what announced projects could produce by 2030. In 2021 to 2025, 7 Mtpa of offtake was announced globally of which only 1.6 Mtpa is firm. Announced volume is not contracted volume, and that gap is the whole of the demand risk.
Why is capital more expensive for a project in an emerging economy?
Because the track record is short: in 2025 only 0.5 percent of announced projects there had secured committed investment against 9 percent worldwide, and capital can reach 15 percent, three times the level of advanced economies. Lenders price the absence of completed files rather than the quality of the plan.
What public money is available before the final investment decision?
Public money arrives first: 6.6 billion USD of development finance institution loans in 2021 to 2025, 38 billion USD of public funding advanced in national policies, and 8 billion USD invested in production in 2025. That layer prices the file before private capital will look at it.
What stops a power-to-liquid project reaching FID?
Four things: an announced pipeline instead of a decision, with 22 Mt at risk without an investment before early 2027; a demand test that fails at below 2 Mtpa firm, as counted in 2025; a cost of capital at 15 percent, also in 2025; and missing infrastructure, with the answer pointing at industrial and port clusters in 2026. Each of the four is testable before you approach a lender.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at pre-FID structuration and want the layers ordered before the file goes out, I run that pass with you through project finance advisory, starting from demand and committed capital rather than from the model. That ordering is the whole of PtL finance and FID.
My work covers neither investment advice nor investment arrangement. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.