We Connect Asia

Hydrogen

PtL Offtake Agreements: What a Power-to-Liquid Fuel Contract Must Cover

10 min read  ·  Dec 2, 2025  ·  By Alex

ptl offtake agreements

A power-to-liquid purchase contract passes four tests before a lender will size any debt against it: a buyer with a credit record, a volume that covers the plant, a duration that covers the loan, which in 2025 ran from 8 to 14 years, and a price that is fixed with risk shared. In addition, All four have to pass at the same time. Specifically, PtL offtake agreements are where that test gets settled, and the branch context sits in the power-to-liquid explainer. Moreover, I write for the person drafting the purchase agreement before the sponsor commits capital. Therefore, i keep those four tests visible through every section below.

I will order this in four steps: what lenders require of the contract, what the demand side has already committed, how the contract closes the gap, and what the fuel is worth once power and carbon dioxide sit inside the price. In fact, Each step ends with the move I would make.

In short

  • Duration: the contract must run 8 to 14 years, the range lenders used in 2025 for these financings.
  • Volume: at least 70 to 80 percent of annual capacity in 2025 investor terms, with 100 percent for some lenders.
  • Price: fixed while the market is nascent in 2025, with risk shared between producer and buyer.
  • Counterparty: a buyer with credit history, a healthy profit and loss statement and a plan to use the volumes.
  • Evidence: announced capacity, memoranda and merchant forecasts stay outside debt sizing until they are firm.
Facebook
Twitter
LinkedIn

In this article

What a power-to-liquid offtake has to answer

Power-to-liquid means making liquid fuel from captured carbon dioxide and renewable electricity.

Also, an offtake agreement is the purchase contract that turns projected revenue into revenue a lender can size against. Consequently, Every word in that sentence earns its place at the table. Therefore, Take-or-pay makes the buyer pay for the contracted volume whether it lifts it or not. However, Merchant volume is whatever is left with no contract behind it. Also, Counterparty risk is the risk that the buyer fails to pay. For example, Tenor is how long the contract runs. Also, The final investment decision is where the sponsor commits the capital. Instead, Debt sizing is how much the banks will lend against contracted cash flow, and they calculate it from contracts rather than forecasts. However, Fixed price and risk sharing are the two levers in the price clause, and they pull against each other.

What this means for you: I would settle these definitions before anyone names a price, because every figure below attaches to one of them, and a disagreement on tenor is a disagreement about the loan.

What lenders require of the contract

Lenders do not assess a power-to-liquid plant, they assess the contract that wraps it. Specifically, The February 2025 World Economic Forum financing study with Kearney found that investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements, that some lenders require 100 percent of the fuel produced covered for the full loan tenor, and that the contract must cover the debt financing tenure of 8 to 14 years.

Therefore, Lenders expect a fixed price while the market is nascent, with a risk-sharing mechanism beside it. Instead, Airlines on average carry a lower credit rating. Therefore, default risk must be spread across parties rather than held by one buyer. Instead, Merchant volume may be excluded from debt sizing, which produces smaller loans than sponsors expect. For example, I read the same requirements from the investor’s side at the page on investing and the final investment decision.

What this means for you: I would model debt against contracted volume only, treat everything above it as unbanked, and expect the loan to shrink as soon as merchant sales sit in the forecast.

What the demand side has already committed

Mandated and targeted demand for sustainable aviation fuel reaches 17.1 Mt/a in 2030, around 5 percent of jet fuel demand, against installed capacity of 4.4 Mt at the end of 2024 and 5.8 Mt that still needs an investment decision by the end of 2026.

Instead, The announced pipeline stood at 12 Mt/a in August 2024, with power-to-liquid at around 15 percent of announced non-operational capacity and total capital expenditure of 19 billion USD to 45 billion USD needed by 2030. In fact, The buying side is narrower than it looks. Consequently, Only three airline groups consumed more than 1 percent of SAF in 2023, more than 80 percent of voluntary demand comes from 15 airlines. Also, the top 20 carriers cover 15.3 Mt of the 16.3 Mt of voluntary commitments for 2030. Meanwhile, I set out the general framing in the overview of offtake agreements.

What this means for you: I would treat demand as concentrated rather than broad, and ask which airline will put its name to my contract before I plan around any of it.

How the contract closes the gap

Five pricing or contract structures had emerged in sustainable aviation fuel offtakes by February 2025. Also, the more risk is shared, the more bankable the contract is. Intermediaries such as trading firms or infrastructure owners can sign instead of an airline, which reduces counterparty risk. Instead, Long-term offtake, contracts for difference and advance market commitments reduce revenue risk and release private investment. In addition, In February 2024 IAG signed a 14-year contract for 785,000 tonnes of e-SAF with Twelve, and that agreement opened up to 645 million USD, including 400 million USD of project equity and 200 million USD of series C, with a 25 million USD construction loan and a 20 million USD green loan.

By February 2025, Brookfield had committed 1.1 billion USD to Infinium after a 75 million USD project equity investment by Breakthrough Energy Catalyst, with bankable offtake agreements behind it. Furthermore, I set out the mechanics in the guide on securing these contracts.

What this means for you: I would always ask who else is signing, because an intermediary next to a thin buyer turns a wish into a contract a bank accepts.

What the fuel has to be worth

The 2023 e-fuels report shows how fast the price question turns into an electricity question: at 50 USD per MWh the power price alone contributes 25 to 35 USD per gigajoule of fuel, or 1,000 to 1,500 USD per tonne of oil equivalent, before any investment or consumable. Specifically, In the same 2023 modelling the levelised cost, the cost per unit over the plant’s life, rises fast once the electrolyser load factor, the share of time it runs, drops below 40 percent. Moreover, That 2023 modelling assumes a 5 percent cost of capital over a 25 year life, with operating cost beyond electricity at 1.5 percent of capital for electrolysis and 3 percent for synthesis, and pairs 30 and 50 USD per MWh with 800 and 2,000 USD per kilowatt of electrolyser.

Captured carbon dioxide costs 20 to 30 USD per tonne from fermentation, 60 to 80 USD per tonne from biomass flue gas and 400 to 670 USD per tonne from direct air capture. I would carry these cash flows in the structure used for infrastructure project finance.

What this means for you: I would lock the power price and the carbon dioxide source before I quote a fuel price, since both sit inside every unit I sell.

What I will not treat as a signed contract

I apply five exclusions, and I date each one. An announcement is not an offtake: the five key questions section of the 2025 review puts cumulative firm purchase agreements below 2 Mtpa. This is 5 percent of what announced projects could produce by 2030. A signed memorandum is not a firm contract: 7 Mtpa of offtake was announced between 2021 and 2025 of which only 1.6 Mtpa is firm. Capacity is not volume: 12 Mt/a was announced in August 2024 against 4.4 Mt installed at the end of 2024. A merchant forecast is not debt-sized revenue: lenders may exclude it from debt sizing, which shrinks the loan. A market habit is not a commitment: in 2024 buyers were still cautious about signing long-term agreements because they could not see where the market was going, while aviation and maritime kept trading at spot prices.

What this means for you: I would hold all five as separate columns in my data room, so that nobody, including me, reads a pipeline as revenue.

What this changes for a Southeast Asian project

The December 2025 Southeast Asia briefing puts regional demand at 4 Mt in 2024, split between Indonesia at 35 percent, Malaysia at 22 percent, Viet Nam at 15 percent and Singapore at 12 percent. Announced regional projects equal 12 percent of current regional demand. Meanwhile, only 6 percent of announced capacity has reached the final investment decision. The region holds 11 Mtpa of potential below 6 USD/kg by 2030, and development finance institutions lent 6.6 billion USD between 2021 and 2025.

The regulatory pull behind that demand sits in the 2024 European Investment Bank consultation. ReFuelEU Aviation reaches 6 percent blending in 2030 and 70 percent in 2050 with an e-fuels share of 35 percent in 2050. Meanwhile, fuelEU Maritime requires a 6 percent cut in emission intensity by 2030 and 80 percent by 2050. EU demand for sustainable liquid fuels runs at 17 mtoe in 2022 and could reach 21 mtoe in 2030 and 34 mtoe in 2035. The same consultation found almost all large-scale European projects lacking the capital commitment to proceed. I map the obligation itself in the page on ReFuelEU purchase obligations.

What this means for you: I would write the contract against the buyer’s regulatory obligation rather than against announced regional demand, because only 6 percent of announced regional capacity had reached the final investment decision by December 2025.

The four lines I would put in front of an offtaker

Line one, duration: the contract must run 8 to 14 years to cover the debt, the range recorded in 2025. Therefore, Line two, volume: at least 70 to 80 percent of annual capacity, and 100 percent of production for some lenders, in the financing terms recorded in 2025. Line three, price: fixed with risk shared, since the fuel cost two to three times conventional jet fuel between 2023 and 2024, and a 10 percent blend at a 2 to 3 times premium adds 3 to 6 percent to a ticket. Line four, credibility: a buyer with credit history, a healthy profit and loss statement and a plan to use the committed volumes. None of these needs a technical argument.

What this means for you: I would put those four lines on a single page in front of the offtaker before any technical discussion, because they are the four answers the lender will ask me for anyway.

Sources

Frequently asked questions

Four things: a buyer with credit history and a plan to use the volumes, a volume covering the plant, a duration covering the loan of 8 to 14 years as recorded in 2025, and a fixed price with risk shared between producer and buyer. Debt sizing is done against those contracted cash flows before the final investment decision, and I look for all four in the same draft rather than in sequence.

Long enough to cover the debt financing tenure, which runs from 8 to 14 years in the financing terms recorded in 2025, with the incentives supporting the purchase aligned to the same tenor. Anything shorter leaves the tail of the loan uncovered, and the contract and the support behind it should end together.

At least 70 to 80 percent of annual capacity in the view of investors in 2025, and some lenders want 100 percent of production covered for the full loan tenor, because merchant sales are hard to count when the market has no established price. Volume left outside the contract sits outside the loan.

Because the power cost and the carbon dioxide source sit inside the fuel price: in the 2023 cost modelling, 50 USD per MWh adds 25 to 35 USD per gigajoule on its own, the cost climbs fast below a 40 percent load factor, and captured carbon dioxide ranges from 20 to 30 USD per tonne to 400 to 670 USD per tonne depending on the source.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are at this point, my offtake agreement structuring work covers the four tests, the volume and tenor you can defend, and the price clause, from the first draft through to the version a lender can size against.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles